4.3.2
Hoisting Transport
1)
Anchor two M10 thread lifting rings to the hangers of the inverter (Fig. 4-7).
Fig. 4-7 Thread lifting rings
2)
Lead the sling through the two lifting rings and fasten the tie-down strap.
3)
Hoist the inverter, and stop to check for safety when the inverter is 100 mm above the ground (Fig. 4-8).
Continue hoisting the device to the destination after ensuring the safety.
Fig. 4-8 Hoist the inverter
4)
Remove the lifting rings and reassemble the sealing screws released before (Fig. 4-7).
NOTE:
The lifting rings and the sling are not within the delivery scope.
4.3.3
Mounting-bracket installation
The procedure to install the
ZGR SOLAR STR 250
on Mounting-bracket is as follows:
The dimensions of the assembled mounting-bracket are as follows:
WARNING
Keep the inverter balanced throughout the hoisting process and avoid collisions with walls or other objects.
Stop hoisting in the event of severe weather, such as heavy rain, thick fog, or strong wind.
NOTICE
The ground surface on which the inverter is to be placed should be covered with a sponge pad, foam cushion
or the like to prevent the inverter bottom from scratches.