5.4.2 Grid connection
Overview of the AC Connection Plug
A B C D E
Object
Description
A
Socket element
B
Adapter
C
Sealing ring
D
Fastening case
E
Cable nut
Procedure
1
Switch off the miniature circuit breaker and secure it against being inadvertently
switched back on.
2
Guide the cable nut, the fastening case with sealing ring and the adapter over the
AC cable.
3 Strip the cable jacket (72mm) and the insulation (8.5mm)
,
cable size 10mm² Max.
Insert bared conductors into the cord end terminal and crimp the contact. The cord
end terminals provided are only suitable for stranded copper wire AWG 10.