SECTION 3 - HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
Rigging and Installing the Condenser
Use the following instructions to install the condenser
The lifting chains along the axis of the
evaporator/condenser shells should not
exceed 90° +/- 10°. A spreader bar may
be required to achieve the +/- 10°.
One chain is required per each lifting
point.
Use lifting chains with working load limit
each at least 40% of the total shell weight.
1. Attach the rigging chains from the overhead lift to
the four lifting holes of the condenser (two at the
top of each end sheet).
2. Lift the condenser and place next to the evaporator.
3. Bolt the end sheets of the evaporator and condens-
er together. Note that the outside surfaces of the
tube sheets must be flush.
Leveling the Evaporator and Condenser
Use the following instructions to level the evaporator
and condenser in both directions within 1/4 in. (6 mm).
1. Check the alignment of the shell by placing a level
on the top of the shell, next to the discharge con-
nection.
2. Check the alignment by placing a level on the tops
of both end sheets.
TABLE 6 -
CONDENSER DIMENSIONS (IN/MM)
SHELL CODE (PIN 7)
LENGTH
WIDTH
HEIGHT
B
96 (2438)
28.2 (716)
35.3 (896)
C
120 (3048)
28.2 (716)
35.3 (896)
D
144 (3658)
28.2 (716)
35.3 (896)
NOTE:
Refer to
for the approximate weight of the condenser. Waterboxes are not shown in Figure 11.
LD17752a
Lifting
Holes
Lifting
Holes
Lifting
Holes
CONDENSER
A
End
Sheet
65°
Min.
90° +/- 10˚
FIGURE 12 -
CONDENSER RIGGING