background image

548086-XIM-C-0814

4

Johnson Controls Unitary Products

PRECAUTIONS DURING BRAZING OF LINES

All outdoor unit and evaporator coil connections are copper-to-copper
and should be brazed with a phosphorous-copper alloy material such
as Silfos-5 or equivalent. DO NOT use soft solder. The outdoor units
have reusable service valves on both the liquid and vapor connections.
Since these units are designed to operate on either R-22 or R-407C,
they have been shipped from the factory with a nitrogen holding charge.
Refer to the Tabular Data sheets for refrigerant charge quantities. The
reusable service valves are provided to evacuate and charge per this
instruction.

Serious service problems can be avoided by taking adequate precau-
tions to assure an internally clean and dry system.

PRECAUTIONS DURING BRAZING SERVICE VALVE

Precautions should be taken to prevent heat damage to service valve
by wrapping a wet rag around it as shown in Figure 4. Also, protect all
painted surfaces, insulation, and plastic base during brazing. After braz-
ing, cool joint with wet rag.

Connect the refrigerant lines using the following procedure:

1.

Remove the cap and Schrader core from both the liquid and vapor
service valve service ports at the outdoor unit. Connect low pres-
sure nitrogen to the liquid line service port.

2.

Braze the liquid line to the liquid valve at the outdoor unit. Be sure
to wrap the valve body with a wet rag. Allow the nitrogen to con-
tinue flowing.

3.

Carefully remove the plugs from the evaporator liquid and vapor
connections at the indoor coil.

4.

Braze the liquid line to the evaporator liquid connection. Nitrogen
should be flowing through the evaporator coil.

5.

Slide the grommet away from the vapor connection at the indoor
coil. Braze the vapor line to the evaporator vapor connection. After
the connection has cooled, slide the grommet back into original
position.

6.

Protect the vapor valve with a wet rag and braze the vapor line
connection to the outdoor unit. The nitrogen flow should be exiting
the system from the vapor service port connection. After this con-
nection has cooled, remove the nitrogen source from the liquid fit-
ting service port.

7.

Vent the nitrogen holding charge in the outdoor unit by opening
both service valves slowly and waiting for the pressure to dissi-
pate. Open both the liquid and vapor valves by removing the
plunger cap and with an allen wrench back out counter-clockwise
until valve stem just touches the chamfered retaining wall. If the
service valve is a ball valve, use a Crescent wrench to turn valve
stem one-quarter turn counterclockwise to open. Do not overturn
or the valve stem may break or become damaged. See “PRECAU-
TIONS DURING BRAZING SERVICE VALVE”.

8.

Replace the Schrader core in the liquid and vapor valves.

9.

Go to SECTION IV or SECTION V for orifice or TXV installation
depending on application.

10. Leak test all refrigerant piping connections including the service

port flare caps to be sure they are leak tight. DO NOT OVER-
TIGHTEN (between 40 and 60 inch - lbs. maximum).

11.

Evacuate the entire 500 microns or less.

12. Replace cap on service ports. Do not remove the flare caps from

the service ports except when necessary for servicing the system.

13. Add the refrigerant charge into the system. Since these units are

designed to operate on either R-22 or R-407C, they have been
shipped from the factory with a nitrogen holding charge. Refer to
the Tabular Data sheets for refrigerant charge quantities.

14. Replace plunger cap finger tight, then tighten an additional 1/12

turn (1/2 hex flat). Cap must be replaced to prevent leaks.

See “System Charge” section for checking and recording system
charge.

Supplied with the outdoor unit is an Orifice for highest sales volume
indoor coil. 

Dry nitrogen should always be supplied through the tubing while it
is being brazed, because the temperature required is high enough
to cause oxidation of the copper unless an inert atmosphere is pro-
vided. The flow of dry nitrogen should continue until the joint has
cooled. Always use a pressure regulator and safety valve to insure
that only low pressure dry nitrogen is introduced into the tubing.
Only a small flow is necessary to displace air and prevent oxidation.

This is not a backseating valve. The service access port has a
valve core. Opening or closing valve does not close service access
port.
If the valve stem is backed out past the chamfered retaining wall,
the O-ring can be damaged causing leakage or system pressure
could force the valve stem out of the valve body possibly causing
personal injury.

 FIGURE 4:  

Heat Protection

A0153-001

Do not install any coil in a furnace which is to be operated during
the heating season without attaching the refrigerant lines to the coil.
The coil is under 30 to 35 psig inert gas pressure which must be
released to prevent excessive pressure build-up and possible coil
damage.

Line set and indoor coil can be pressurized to 250 psig with dry
nitrogen and leak tested with a bubble type leak detector. Then
release the nitrogen charge.

Do not connect manifold gauges unless trouble is suspected.
Approximately 3/4 ounce of refrigerant will be lost each time a stan-
dard manifold gauge is connected.

Never attempt to repair any brazed connections while the system is
under pressure. Personal injury could result.

NOTICE

Summary of Contents for GCGA SERIES

Page 1: ...ndoor out door unit combinations elevation differences or total line lengths Refer to Application Data covering General Piping Recommendations and Refrigerant Line Length Part Number 247077 SECTION II...

Page 2: ...ion must be observed to ensure a system that will give maximum performance with minimum service 4 The unit should not be operated at outdoor temperatures below 50 F without an approved low ambient ope...

Page 3: ...for approved system combinations as specified in tabular data sheet The initial charge given is applicable for total tubing lengths up to 15 feet 4 6 m See Application Data Part Number 247077 for inst...

Page 4: ...one quarter turn counterclockwise to open Do not overturn or the valve stem may break or become damaged See PRECAU TIONS DURING BRAZING SERVICE VALVE 8 Replace the Schrader core in the liquid and vap...

Page 5: ...s as a reservoir c Bulb should be insulated using thermal insulation provided to protect it from the effect of the surrounding ambient tempera ture Cover completely to insulate from air stream SECTION...

Page 6: ...r than the rec ommended value Remove recover charge if the measured liquid pressure is above the recommended value Condenser subcooling is obtained by calculating the difference of the saturated refri...

Page 7: ...75 49 90 57 105 65 120 72 135 79 150 85 165 90 76 49 91 58 106 66 121 73 136 79 151 85 166 91 77 50 92 58 107 66 122 73 137 80 152 86 167 91 78 50 93 59 108 67 123 74 138 80 153 86 168 91 79 51 94 60...

Page 8: ...lace it on an out side wall or where it is exposed to the radiant effect from exposed glass or appliances drafts from outside doors or supply air grilles 6 Route the 24 volt control wiring NEC Class 2...

Page 9: ...WER WIRING CONTACTOR TERMINALS COIL GND LUG C Y R G W Y R G W POWER WIRING CONTROL WIRING FACTORY WIRING 24 VOLT CONTROL WIRING MINIMUM 18 GA WIRE NEC CLASS 2 FURNACE OR AIR HANDLER TERMINAL BLOCK ROO...

Page 10: ...actor R 24 Volt Hot Heat XFMR R 24 Volt Hot Heat XFMR E W1 Emergency Heat E W1 Emergency Heat AUX Auxiliary Heat R 24 Volt Hot Cool XFMR Y2 Second Stage Compressor Connection of the C terminal 24 Volt...

Page 11: ...terminal 24 Volt common is optional when used with batteries Thermostat Installer Setup 0170 System Type must be set to 1 1 Heat 1 Cool Conventional Refer to AH documentation for W1 and W2 electric he...

Page 12: ...ct the owner on proper operation and maintenance of all other system components MAINTENANCE 1 Dirt should not be allowed to accumulate on the outdoor coils or other parts in the air circuit Clean as o...

Page 13: ...TORS MAY BE USED ON ACTUAL UNIT WIRING MUST CONFORM TO NATIONAL AND LOCAL CODES IF ANY OF THE ORIGINAL WIRE SUPPLIED WITH THIS UNIT MUST BE REPLACED IT MUST BE REPLACED WITH TYPE 105 C THERMOPLASTIC O...

Page 14: ...2 T1 24 VAC CTRL CIRCUIT 20VA MIN BLU BLU RED BLK BRN RED BLK GND LUG GND CONTACTOR OPTIONAL LOW VOLTAGE WIRING 2 3 FIELD WIRING CTRL CIRCUIT BLK YEL PNK YEL PNK HPS COLOR CODE BLK BLACK BLU BLUE BRN...

Page 15: ...LL BE REMOVED IF LOW AMBIENT KIT IS INSTALLED YELLOW WIRE WILL BE REMOVED IF PRESSURE SWITCH KIT IS INSTALLED IF ANY OF THE ORIGINAL WIRE SUPPLIED WITH THIS UNIT MUST BE REPLACED IT MUST BE REPLACED W...

Page 16: ...548086 XIM C 0814 16 Johnson Controls Unitary Products NOTES...

Page 17: ...f applicable Electrical Line Voltage Outdoor Unit Model Outdoor Unit Serial Filter Thermostat Accessories Filter Location s Connections Per Installation Instructions and Local Codes Gas piping is conn...

Page 18: ...th the owner s manual Explain thermostat use and programming if applicable to owner Cycle Test Operate the unit through several heating cycles if applicable from the thermostat noting and correcting a...

Reviews: