All L.P./propane gas equipment must conform to the safety
standards of the National Fire Protection Association.

For satisfactory operation, L.P./propane gas pressure must be
8.8 inch W.C at the unit under full load. Maintaining proper gas
pressure depends on three main factors:

1. The vapor ization rate which depends on (a) the

temperature of the liquid and (b) the “wetted surface” area
of the container or containers.

2. The proper pressure regulation. (Two-stage regulation is

recommended from the standpoint of both cost and
efficiency.)

3. The pressure drop in the lines between regulators and

between the second stage regulator and the appliance.
Pipe size required will depend on the length of the pipe run
and the total load of all appliances.

Complete information regarding tank sizing for vaporization,
recommended regulator settings, and pipe sizing is available
from most regulator manufacturers and L.P./propane gas
suppliers.

L.P./propane gas is an excellent solvent and special pipe
compound must be used when assembling piping for this gas
as it will quickly dissolve white lead or most standard
commercial compounds. Shellac base compounds such as
Rectorseal #5 are satisfactory for this type of gas.

Check all connections for leaks when piping is completed,
using a soap solution. NEVER USE A FLAME.

VENT AND COMBUSTION AIR HOODS

Two vent hoods and a combustion air hood (with screens) are
shipped attached to the blower housing in the blower
compartment. These hoods must be installed to assure proper
unit function. All hoods must be fastened to the outside of the
gas heat access panel with the screws provided in the bag also
attached to the blower housing.

The screen for the combustion air intake hood is secured to the
inside of the access panel opening with four fasteners and the
screws used for mounting the hood to the panel. The top flange
of this hood slips in under the top of the access panel opening
when installing. Refer to Vent and Combustion Air Hood figure.

Each vent hood is installed by inserting the top flange of the
hood into the slotted opening in the access panel and securing
in place.

OPTIONAL ECONOMIZER/MOTORIZED DAMPER
RAIN HOOD

The instruction for the optional economizer/motorized damper
rain hood can be found in form 44-320-2. Use these instructions
when field assembling an economizer rain hood onto a unit.
The outdoor and return air dampers, the damper actuator, the
damper linkage, the outdoor and return air divider baffles, and
all the control sensors are factory mounted as part of the
“Factory installed” economizer option.

ENTHALPY SET POINT ADJUSTMENT

Remove the economizer access panel from the unit to check
the following adjustments. Loosen but do not remove the two
panel latches.

CAUTION: Extreme care must be exercised in turning both the

setpoint and minimum position adjusting screws to
prevent twisting them off.

6. The enthalpy set point may now be set by selecting the desired

setpoint shown in the Adjsuting Enthalpy Setpoint figure. Adjust
as follows:

For a single enthalpy operation, carefully turn the set
point adjusting screw to the “A”, “B”, “C” or “D” setting
corresponding to the lettered curve. 

For a dual enthalpy operation, carefully turn the set point
adjusting screw fully clockwise past the “D” setting.

7. To check that the damper blades move smoothly without

binding, carefully turn the minimum position adjusting
screw fully clockwise and then energize and de-energize
terminals  “R” to “G”. With terminals “R” to “G” energized,
turn the minimum position screw counterclockwise until the
desired minimum position has been attained.

8. Replace the economizer access panel. Reposition the two

latches horizontally and retighten the screws.

POWER EXHAUST/BAROMETRIC RELIEF DAMPER
AND RAIN HOOD OPTION

The instructions for the power exhaust/barometric relief
damper and rain hood can be found in form  44-320-10. The
exhaust fan, all supporting brackets, angles, and the wiring are
factory installed as part of the power exhaust option.

All of the components, including the dampers, hardware, and
mounting instructions are shipped in a single package external
from the unit. The hood must be field assembled and installed.
Power exhaust is not available as a field installed option.

VENT AIR
OUTLET
HOODS

SLOTTED
OPENINGS IN 
ACCESS PANEL

COMBUSTION
AIR INTAKE
HOOD

GAS HEAT
ACCESS
PANELS

FIG. 8 - VENT AND COMBUSTION AIR HOODS

530.18-N6Y

Unitary Products Group

7

Summary of Contents for D2CG180

Page 1: ...rsion Accessory USA 530 18 N6 2V High Altitude Accessory Nat Gas 530 18 N6 3V High Altitude Accessory Propane 530 18 N13Y Coil Guard Installation Renewal Parts Refer to the Renewal Parts Manual for co...

Page 2: ...7 Four And Six Point Loads 12 8 Supply Air Blower Perf 15 Ton 13 9 Supply Air Blower Perf 20 Ton 14 10 Static Resistances 15 11 Power Exhaust Performance 15 12 Blower Motor and Drive Data 15 13 Limit...

Page 3: ...ame other than a YORK roof curb gasketing must be applied to all surfaces that come in contact with the unit underside 5 Maintain level tolerance to 1 2 inch maximum across the entire length or width...

Page 4: ...ductwork to accommodate the damper Using the holes in the hood flanges as a template drill 9 64 inch dia 26 drill holes into the ductwork and secure with the screws provided CAUTION If outdoor air in...

Page 5: ...ing to the unit waterproof type connectors MUST BE USED so that water or moisture cannot be drawn into the unit during normal operation The above waterproofing conditions will also apply when installi...

Page 6: ...or John Crane may be used 4 All piping should be cleaned of dirt and scale by hammering on the outside of the pipe and blowing out the loose dirt and scale Before initial start up be sure that all of...

Page 7: ...securing in place OPTIONAL ECONOMIZER MOTORIZED DAMPER RAIN HOOD The instruction for the optional economizer motorized damper rain hood can be found in form 44 320 2 Use these instructions when field...

Page 8: ...FIG 9 ENTHALPY SETPOINT ADJUSTMENT 530 18 N6Y 8 Unitary Products Group...

Page 9: ...6 0 43 3 COMPRESSOR Qty Per Unit 10 TON TANDEM 1 2 5 TON HERMETIC 1 AIR FILTERS QUANTITY PER UNIT 16 X 20 X 2 4 QUANTITY PER UNIT 16 X 25 X 2 4 QUANTITY PER UNIT 18 X 24 X 2 5 TOTAL FACE AREA sq ft 15...

Page 10: ...84 9 100 460 3 60 19 2 124 9 6 62 1 2 1 5 7 2 42 4 50 575 3 60 15 4 100 7 7 50 1 2 0 5 5 9 33 9 40 DCG240 208 230 3 60 38 4 248 38 4 248 1 4 1 4 2 7 5 21 0 19 4 115 1 111 6 125 460 3 60 19 2 124 19 2...

Page 11: ...ic meters gas meters regulators and relief equip R E T U R N A I R S U P P L Y A I R B O T T O M S U P P L Y A N D R E T U R N A I R O P E N I N G S S e e N o t e B P O W E R W I R I N G E N T R Y A C...

Page 12: ...NOTE These weights are with economizer and the largest blower motor available UNIT 6 POINT LOADS LBS TOTAL A B C D E F 180 2300 351 367 392 416 399 375 240 2500 334 350 426 502 481 407 NOTE These weig...

Page 13: ...7 3 0 2 7 0 4 3 5 3 1 915 5 0 1 1 2 6 2 4 0 8 3 1 2 8 0 5 3 6 3 2 0 2 4 1 3 7 965 4 0 1 2 2 7 2 5 0 9 3 2 2 9 0 6 3 7 3 3 0 4 4 4 3 9 0 2 5 0 4 5 980 3 5 1 3 2 9 2 6 1 0 3 4 3 0 0 7 3 8 3 4 0 5 4 5 4...

Page 14: ...4 1 1 5 0 4 2 0 6 5 9 5 0 0 1 6 7 5 7 950 3 5 1 7 4 2 3 6 1 3 5 1 4 3 0 8 6 0 5 1 0 2 6 9 5 8 965 2 5 1 9 4 5 3 8 1 5 5 4 4 5 1 0 6 3 5 3 0 4 7 2 6 1 0 1 8 5 7 1 995 2 0 2 1 4 6 3 9 1 6 5 5 4 7 1 1 6...

Page 15: ...65 1190 BK80 7 75 7 4 1 BX68 69 8 1 20 TON Stan dard 870 1025 7 5 213T 89 1VP68 6 75 5 5 6 52 1 3 8 BK120 11 75 11 4 1 3 16 BX83 84 8 1 High Speed Access 950 1120 BK110 10 75 10 4 1 3 16 BX81 81 8 1 1...

Page 16: ...rating efficiency ECONOMIZER SINGLE OR DUAL WITH POWER EXHAUST This system operates as specified above with one addition The power exhaust motor is energized whenever the economizer is chosen by the e...

Page 17: ...here are two separate gas valves in the furnace Each valve contains a main and a redundant valve The redundant valves are located upstream of the main gas valves Should either or both of the main gas...

Page 18: ...units If gas pressure is outside these limits contact the local gas utility for corrective action MANIFOLD GAS PRESSURE ADJUSTMENT Small adjustments to the high fire gas flow may be made by turning th...

Page 19: ...within the limitations shown in the Applications Data Table 2 Pulleys can be adjusted in half turn increments 3 The tension on the belt should be adjusted as shown in the Belt Adjustment figure Start...

Page 20: ...2 With the furnace turned on measure the time needed for one revolution of the hand on the smallest dial on the meter A typical gas meter usually has a 1 2 or a 1 cubic foot test dial 3 Using the numb...

Page 21: ...E Exercise care when cleaning the coil so that the coil fins are not damaged Do not permit the hot condenser air discharge to be obstructed by overhanging structures of shrubs BURNER PILOT Periodicall...

Page 22: ...tat fan switch set to AUTO a Set fan switch to ON If blower motor runs go to Step f If it does not check to see if line voltage is being supplied to the contacts of the contactor M3 and if the contact...

Page 23: ...T CHECKOUT b Check all wiring between the ignitor control and the gas valve Check to make sure the ground connections are intact c If the wiring is intact check for 24 volts across terminals PV and CO...

Page 24: ...and information from OUR current parts list for this unit are available to your servicing contractor through our local distributor The name and address of our nearest distributor may be obtained by co...

Reviews: