61
GLOBAL
INDUSTRIES, INC.
Drag Conveyors
10230011
2016-06-14
Intermediate Right Angle Rack and Pinion Gate Assembly
Assembly
26
Optional
Field cut and remove a 37 1/2” length segment
from the intermediate bottom as shown
(see
the example below)
. Center the cut between
36” [914 mm] bolt centers. Position and install
the gate to the conveyor along with the weather
cover and intermediate discharge hopper.
Electric rack and pinion gates are installed the
same way.
use 3/8” bolts
and flange nuts
NOTE: Bars on gates are made to be flush
with intermediate bottoms. Grind smooth any
unevenness.
ELECTRIC RACK AND PINION GATE
INTERMEDIATE SECTION
WEATHER
COVER
ROPE WHEEL
RACK AND PINION GATE
INTERMEDIATE DISCHARGE HOPPER
37 1/2” (+1/16” - 0) [953 mm]
caulk as needed
GRAIN FLOW
DIRECTION
towards
head
section
towards
tail
section