<3. INSTALLATION, PIPING, AND WIRING>
3-1
IM 12E04A02-02E
3. INSTALLATION, PIPING, AND WIRING
3.1 Installation
3.1.1 Unpacking
The scattered-light turbidimeter is shipped only after being packed so as not to be damaged
during transportation. When the turbidimeter is delivered, unpack the meter carefully. If the
turbidimeter with a sampling system is delivered, unpack them near the location where they are
to be installed.
3.1.2 Installation
Location
The scattered-light turbidimeter should be installed in a location where:
(1) rainwater cannot get inside, such as in a building or a cubicle,
(2) there is little vibration,
(3) corrosive gases are not present,
(4) there is low humidity,
(5) temperature changes are kept to a minimum and the temperature is maintained between -5
to 50 °C,
(6) there is enough clearance for maintenance and maintenance work can be easily done,
(7) drainage can be provided.
3.1.3 Installation
Installation of the scattered-light turbidimeter differs depending on whether the sampling system
is provided or not. If the sampling system is provided, secure the entire system with anchor bolts
(M12 (12 mm) bolts) to a well-drained “concrete base”. If the sampling system is not provided,
mount the detector and converter onto pipes (nominal diameter of 50 mm) or racks with the
special mounting bracket. (See Model Code Option Speci
fi
cation.)
3rd Edition : May. 31, 2010-00
Summary of Contents for Vigilant Plant EXA TB Series
Page 49: ...Blank Page ...
Page 59: ...Blank Page ...
Page 119: ...Blank Page ...
Page 125: ...Blank Page ...
Page 127: ...Blank Page ...
Page 133: ...Blank Page ...