background image

11

MAINTENANCE

SCHEDULE:

Blow down control as follows when boiler is 
in operation.

• Daily if operating pressure is above 15 psi.
• Weekly if operating pressure is below 15 psi.

• Remove head assembly and inspect water-

side components annually.

Replace head

assembly if any of the internal components are
worn, corroded or damaged or if control no longer
operates properly.

• Inspect the float chamber and equalizing piping

annually.

Remove all sediment and debris.

Replace head mechanism every 5 years.

More frequent replacement may be required when 
severe conditions exist.

Replacement parts are available from your local
authorized McDonnell & Miller Distributor.

The use of parts or components other than those
manufactured by McDonnell & Miller will void all 
warranties and may affect the units’ compliance with
listings or regulating agencies.

BLOW DOWN PROCEDURE:

When blowing down a control at pressure, the blow
down valves should be opened slowly.The piping
needs to be warmed up and stagnant water in the
drain piping needs to be pushed out. Suddenly
opening a blow down valve causes steam to
condense, which can create water hammer.
Damage to components can occur when water
hammer occurs due to improper blow down piping.

For these reasons, McDonnell & Miller recommends
a dual valve blow-down system for each control.

Blow down the control when the water in the boiler
is at its normal level and the burner is on.

NOTE:

Refer to page 2 for switch operating points.

• Open upper valve (#1)
• Slowly open the lower valve (#2)
• Water in the sight glass should lower.
• As the water in the sight glass lowers, the

pump should turn on.

• As the water continues to lower in the sight

glass, the burner should turn off.

• Slowly close the lower valve (#2).
• Close the upper valve (#1)
• The water level in the sight glass should rise, first
turning on the burner and then turning off the pump.

NOTE:

On manual reset models, the reset button

will need to be pressed after the water level has
been restored before the burner will operate.

To prevent serious personal injury from steam
pipe blow down, connect a drain pipe to the
control opening to avoid exposure to steam
discharge.

Failure to follow this caution could cause
personal injury.

!

CAUTION

NOTE

More frequent blow-down may be necessary
due to dirty boiler water and/or local codes.

Valve #2

Valve #1

NOTE

The control may need to be inspected and
cleaned more frequently on systems where there
is the potential of excessive scale or sludge
build-up. This includes systems:

• With high raw water make-up
• With no condensate return
• With untreated boiler water
• Where significant changes have been

made to the boiler-water chemical
treatment process

• With oil in the boiler water

NOTE

If this sequence of operation does not occur as described,
immediately close all valves, turn off the boiler and
correct the problem. Inspection/cleaning of the float
mechanism may be required to determine why the 
control was not working properly. Retest the control
after the problem has been identified and corrected.

Summary of Contents for McDonnell & Miller 42S-N Series

Page 1: ...INSTRUCTION MANUAL MM 231G...

Page 2: ...ATER LINE PUMP OFF BURNER OFF BURNER CUT OFF LEVEL AT CAST LINE 1 3 8 35mm CUT OFF LEVEL NORMAL BOILER WATER LINE CUT OFF LEVEL PUMP OFF PUMP ON 3 4 19mm OPERATION Maximum Pressure 50 psi 3 5 kg cm2 E...

Page 3: ...Cut Off Pump Controller Must be Installed INSTALLATION TOOLS NEEDED Two 2 pipe wrenches one 1 flathead screw driver and pipe sealing compound IMPORTANT Follow the boiler manufacturer s instructions al...

Page 4: ...as depicted in the diagram to the bottom right OR If gauge glass tappings F and G are greater than 14 356 mm apart invert the black Y casting H as depicted in the diagram to the bottom right and inst...

Page 5: ...P Screw reducer bushing Q nipple R and blow off valve S into bottom 1 NPT tapping T Screw lower union tailpiece V with nut U into either 1 2 NPT lower tapping W X Screw 1 2 NPT pipe plug into unused...

Page 6: ...rient 1 2 NPT tapping FF with 1 2 tapping on control GG b Mount and pipe control HH on vertical equalizing pipes JJ at the required elevation as determined in Step 1 c Install gauge glass and other tr...

Page 7: ...h could result in property damage personal injury or death WARNING Switch Operation Boiler feed pump off burner on Boiler feed pump on burner on Boiler feed pump on burner off 1 2 5 6 1 2 5 6 1 2 5 6...

Page 8: ...n NOTE To help insure most effective operation balance boiler feed pump s to deliver required water feed rate to match boiler steaming requirements 1 Main Line Switch For burner circuits within the sw...

Page 9: ...ating ranges are shown on page 2 in the Operation section OFF ON If the burner comes on immediately turn the boiler off and make the necessary corrections Failure to follow this warning could cause an...

Page 10: ...urner is on slowly open the blow down valve NN until it is fully open Watch the gauge glass D to see that the water level drops Close the valve after verifying that the pump comes on and the burner sh...

Page 11: ...s on NOTE Refer to page 2 for switch operating points Open upper valve 1 Slowly open the lower valve 2 Water in the sight glass should lower As the water in the sight glass lowers the pump should turn...

Page 12: ...ngs and other wear parts or consumables all of which are not warranted except as otherwise provided in the quotation or sales form will be free from defects in material and workmanship for a period of...

Reviews: