background image

3

1"

The 42S and 42S-N controls are
installed so that the horizontal cast line
on the body is 

1

a

a

” (35mm) below

the

boiler’s 

normal

water level, 

but not

lower than the lowest, safe permissi-
ble water level, as determined by the
boiler manufacturer.

The 42S-A controls are installed in boil-
er’s gauge glass tappings. The horizontal
cast line should be approximately 

1” (25

mm) above

the bottom of the glass.

Verify that this level is

not below the

lowest, safe permissible water level,
as determined by the boiler manufac-
turer.

STEP 1 - Determine the Elevation at Which the
Low Water Cut-Off/Pump Controller Must be Installed

INSTALLATION –

TOOLS NEEDED:

Two (2) pipe wrenches, one (1) flathead screw
driver, and pipe sealing compound.

IMPORTANT:

Follow the boiler manufacturer's

instructions along with all applicable codes and
ordinances for piping, blow down valve and water
gauge glass requirements.

1

3

/

8

"

STEAM  EQUALIZING PIPE

VERTICAL  EQUALIZING PIPE

BLOW DOWN VALVE

NORMAL BOILER
WATER LINE

LOW WATER
CUT-OFF/PUMP CONTROLLER

BURNER CUT-OFF
LEVEL AT CAST LINE

LOWEST
PERMISSIBLE 
WATER LEVEL

(35mm)

WATER

EQUALIZING

PIPE

 STEAM  EQUALIZING PIPE

VERTICAL  EQUALIZING PIPE

BLOW DOWN VALVE

LOW WATER
CUT-OFF/PUMP CONTROLLER

BURNER CUT-OFF
LEVEL AT CAST LINE

WATER

EQUALIZING

PIPE

1

3

/

8

"

NORMAL BOILER
WATER LINE

LOWEST
PERMISSIBLE 
WATER LEVEL

(35mm)

Series 42S

Series 42S-N

Summary of Contents for McDonnell & Miller 42S-N Series

Page 1: ...INSTRUCTION MANUAL MM 231G...

Page 2: ...ATER LINE PUMP OFF BURNER OFF BURNER CUT OFF LEVEL AT CAST LINE 1 3 8 35mm CUT OFF LEVEL NORMAL BOILER WATER LINE CUT OFF LEVEL PUMP OFF PUMP ON 3 4 19mm OPERATION Maximum Pressure 50 psi 3 5 kg cm2 E...

Page 3: ...Cut Off Pump Controller Must be Installed INSTALLATION TOOLS NEEDED Two 2 pipe wrenches one 1 flathead screw driver and pipe sealing compound IMPORTANT Follow the boiler manufacturer s instructions al...

Page 4: ...as depicted in the diagram to the bottom right OR If gauge glass tappings F and G are greater than 14 356 mm apart invert the black Y casting H as depicted in the diagram to the bottom right and inst...

Page 5: ...P Screw reducer bushing Q nipple R and blow off valve S into bottom 1 NPT tapping T Screw lower union tailpiece V with nut U into either 1 2 NPT lower tapping W X Screw 1 2 NPT pipe plug into unused...

Page 6: ...rient 1 2 NPT tapping FF with 1 2 tapping on control GG b Mount and pipe control HH on vertical equalizing pipes JJ at the required elevation as determined in Step 1 c Install gauge glass and other tr...

Page 7: ...h could result in property damage personal injury or death WARNING Switch Operation Boiler feed pump off burner on Boiler feed pump on burner on Boiler feed pump on burner off 1 2 5 6 1 2 5 6 1 2 5 6...

Page 8: ...n NOTE To help insure most effective operation balance boiler feed pump s to deliver required water feed rate to match boiler steaming requirements 1 Main Line Switch For burner circuits within the sw...

Page 9: ...ating ranges are shown on page 2 in the Operation section OFF ON If the burner comes on immediately turn the boiler off and make the necessary corrections Failure to follow this warning could cause an...

Page 10: ...urner is on slowly open the blow down valve NN until it is fully open Watch the gauge glass D to see that the water level drops Close the valve after verifying that the pump comes on and the burner sh...

Page 11: ...s on NOTE Refer to page 2 for switch operating points Open upper valve 1 Slowly open the lower valve 2 Water in the sight glass should lower As the water in the sight glass lowers the pump should turn...

Page 12: ...ngs and other wear parts or consumables all of which are not warranted except as otherwise provided in the quotation or sales form will be free from defects in material and workmanship for a period of...