Versant 80 Press
Customer Expectation & Installation Guide
Follow-up
Visit the site and verify that all requirements have been met. If the site is not ready, attempt to resolve any readiness conflicts.
Perform ongoing site check updates until the site is ready.
When the site is ready, begin the installation process used in the district. Ensure that any optional letters of agreement
concerning space requirements are processed properly in the district.
Customer Site Description
Special Customer Site Considerations
1.
(USA only) Are union workers at the loading dock and/or the installation site?
Yes
No
2.
If yes, may the carrier move the equipment at the loading dock and/or the installation site?
Yes
No
3.
Can the delivery be made during normal business hours?
Yes
No
4.
If no, identify any special delivery instructions on the Analyst Site Worksheet, located later in this chapter.
Yes
No
Docks
1.
Is there a loading dock?
Yes
No
2.
Is the dock accessible to a truck/trailer for delivery?
Yes
No
Write any special instructions for the truck driver:
3.
Does the dock have load/dock levelers?
Yes
No
4.
Does the dock area have adequate space for unloading the Press?
Yes
No
NOTE:
If the answer to
any
of the above questions is
No
, then a fork lift will be required to unload the modules from the truck to
the floor/ground level.