V 012 - Protection Module Asymmetry [47]
Commissioning: Asymmetry Protection
Object to be tested
Test of the asymmetry protection elements.
Necessary means
•
3-phase AC voltage source
•
Timer for measuring of the tripping time
•
Voltmeter
Testing the tripping values (Example)
Set the pickup value for the voltage in the negative phase sequence to 0.5 Vn. Set the tripping delay to 1 s.
In order to generate a negative phase sequence voltage interchange the wiring of two phases (VL2 and VL3).
Testing the trip delay
Start the timer and abrupt change (switch) to 1.5 times of the set tripping value. Measure the trip delay.
Successful test result
The measured threshold values and trip delays comply with those specified in the adjustment list. Permissible
deviations/tolerances can be taken from the Technical Data.
EN MRU4 10/09
Page 275