Original operation manual
2K GEL UNIT
25
2KGel_14025_25015_BAoDB_en_1701 • rs
Operation
5 Operation
Prerequisites:
➤
The machine must be correctly installed and fully assembled.
➤
Only put the machine into operation if you are equipped with the prescribed
personal protective equipment. Details on this can be found in chap. 2.5.4
➤
The processing material must be available in sufficient quantity.
Furthermore, two appropriate collecting vessels are required for catching
excessive material. These containers are not included in the scope of delivery.
Observe the safety data sheet of the respective material manufacturer when
processing and storing acrylate gels and silicate injectors.
WARNING
If fluid pumps run dry, this can lead to fire or an explosion due to the
resulting friction heat.
➤
During operation ensure that the drums never run empty. Never leave
the machine running when unattended.
➤
However, if this were to happen, bring the respective pump to an
immediate standstill and add material.
5.1 Putting the machine into operation
Checklist:
➤
Check if all safety features are present and fully functional
➤
During commissioning (flushing), check that all machine parts are leak-tight
and tighten the connections if necessary.
➤
Make sure that the machine is properly grounded
Overview of the work steps during commissioning:
1.
Put the flush pump into operation
2.
Flush out the remains of the test substance
3.
Fill the machine with processing material and ventilate
5.1.1 Putting the flush pump into operation
The flush pump must always be ready for operation during work, in order
that all parts that have come into contact with the mixed material can be
flushed at any time within the specified pot life!
You will need:
➤
the cleaning agent pertaining to the material being processed and
recommended by the material manufacturer in an open container
➤
an additional collecting vessel for the cleaning agent that is flushed out.