4.3
Wieland Electric | BA000349 | 05.2007
4 |
Electrical Installation
Proceed as follows to connect the field distributor to the energy bus:
1. Remove the fastening screws of the hood and slightly lift the hood.
2. If necessary: Remove the electrical plug connection X8 between upper and lower part
and remove the upper part.
3. Remove the two fastening screws, open up the base and place the flat cable inside in the
right direction (according to the coding).
4. Close the base and secure it with the two fastening screws.
Procedure
Procedure
Hood fastening screws
Opened base
Flat cable inserted and base closed
Summary of Contents for podis MOT FP C
Page 2: ......
Page 22: ...Wieland Electric BA000349 05 2007 podis MOT FP C CM CP I IO RS485 SEW Device Description 2...
Page 24: ...3 Wieland Electric BA000349 05 2007 Mechanical Installation Assembly 3...
Page 44: ...5 Wieland Electric BA000349 05 2007 Commissioning 5...
Page 46: ...6 Wieland Electric BA000349 05 2007 Operation 6...
Page 62: ...9 6 Wieland Electric BA000349 05 2007 Appendix 9...
Page 63: ......
Page 64: ......