Benchmark 5000-6000 Boiler Installation & Startup Manual
SECTION 2:
INSTALLATION
OMM-0123_E
• GF-207 • 12/17/2019 Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST Page
35
of
95
Sequencing Isolation Valve Installation Instructions
1.
Install the sequencing isolation valve in the boiler’s hot water outlet pipe (Figure 2-18).
Figure 2-18: Sequencing Isolation Valve Installed
2.
Find the unused black cable, coiled inside the unit’s enclosure. One end is connected to
the DELAYED INTERLOCK IN terminals in the I/O board, while the other end contains a
Molex connector with a cap containing a jumper wire inserted in it (this jumper wire allows
units that do not have a sequencing isolation valve to operate normally).
3. Remove the cap (with jumper wire attached) from the Molex connector and dispose of it.
Figure 2-19: Sequencing Isolation Valve Molex Connector and Jumper Wire
4. Plug the Molex connector
into the sequencing isolation valve’s connector.
HOT WATER
OUTLET
SEQUENCING
ISOLATION VALVE
MOLEX CONNECTOR
JUMPER
CAP