background image

19 

 

START UP INSTRUCTIONS 

 
 

• After installation is completed rotate the bypass handles to the 

bypass position

  

  (see bypass valve diagram page ). 
• Turn on water and check for leaks. 
• Fully open a cold water faucet. 
• Allow water to run until clear to rid pipes of debris which may have occurred during installation. 
• The system is now ready for filling with water and for testing. 

 
 

1.  With the bypass valve in the bypass position, manually pour enough water into the brine tank to reach the 

top of the air check valve. 

 

2.  Press  and  hold  the  REGEN  button  until  the  motor  starts.  Release  button.  Wait  until  the  display  reads 

“BACKWASH” and the remaining time is counting down. Unplug transformer to prevent valve from moving 
to the next cycle. 

 

3.  Open the inlet handle of the bypass valve very slightly allowing water to fill the tank slowly in order to expel 

air. 
CAUTION: If water flows too rapidly there will be a loss of media. 

 

4.  When the water is flowing steadily to the drain without the presence of air, restore power and momentarily 

press 

the REGEN button to advance the control to the “BRINE” position. 

 

5.  Fully open the inlet bypass valve handle (bypass is now in the diagnostic position). 

Check to verify that water is being drawn from brine tank. 
There should be a slow flow to the drain. 
Allow two minutes for the media bed to settle. 

 

6. 

Momentarily press REGEN again until the display reads “2 BACKWASH” and the “time remaining” numbers 
are counting down. The “2” flashes. 

 

7.  Momentarily  press  REGEN  again  until  the  display 

reads “RINSE”. Unplug transformer. There should be a 

rapid flow to the drain. Allow to run until steady, clear, and without air. 
Restore power. 

 

8.  Set bypass valve handles to the normal operating position 
 
9.  Momentarily press REGEN again until the display read

s “FILL”. 

Allow the brine tank to fill automatically. 
It will fill  with the proper volume of water for the first regeneration after the  unit will automatically return to 
the service position. If not filling automatically, press REGEN to advance the valve to service. 

 

10. 

While the brine tank is filling, load it with water softener salt.

 

Summary of Contents for Deluxe Series

Page 1: ...PURPOSES AND TECHNICAL GUIDANCE IT IS STRONGLY RECOMMENDED THAT QUALIFIED DEALER SERVICE PERSONNEL BE CONTACTED IN THE EVENT OF AN UNKNOWN INTERRUPTION OF SERVICE OR APPARENT PRODUCT MALFUNCTION AN A...

Page 2: ...LATION INSTRUCTIONS This unit has a control valve which enables the setting of not only the length of each regeneration cycle but also the order in which cycles steps of regeneration occur The followi...

Page 3: ...2 CONTROL VALVE SPECIFICATIONS...

Page 4: ...service the valve include one small blade screw driver one large blade screw driver pliers and a pair of hands A plastic wrench is available which eliminates the need for screwdrivers and pliers Disa...

Page 5: ...nse cycle or have the regenerant prefill before regeneration If the OEM chooses to have the regenerant prefill before regeneration the prefill starts four hours before the regeneration time set During...

Page 6: ...5 Table 4 Down Flow Softener Program Codes Table 5 Up Flow Softener Program Codes Table 6 Regenerating Filter Program Codes Table 7 Non Regenerating Filter Program Codes...

Page 7: ...on time The user can cancel the request by pressing and releasing the REGEN button This method of manually initiating regeneration is not allowed when the system is set to on 0 i e immediately regener...

Page 8: ...as time of day gallons remaining or days remaining before regeneration current ow rate or total gallons used are shown When stepping through a procedure if no buttons are pressed within ve minutes th...

Page 9: ...d on the printed circuit board Following is an explanation of the options Off Feature not used dPon0 If the dP switch is closed for an accumulative time of 2 minutes a regeneration will occur immediat...

Page 10: ...t Gallons Capacity using or buttons AUTO reserve capacity automatically estimated and gallons capacity automatically calculated from grains capacity and water hardness oFF regeneration based on day ov...

Page 11: ...lons using the or buttons The choices are Relay Actuation Time After the start of a regeneration the amount of time that should pass prior to activating the relay The start of regeneration is de ned a...

Page 12: ...11 SETTING OPTIONS TABLE STEP 1I STEP 2I STEP 3I STEP 4I 4 Reserve capacity estimate is based on history of water usage...

Page 13: ...on water to the unit while also providing untreated water to the distribution system See Figure 1 2 Bypass Position The inlet and outlet handles point to the center of the bypass The system is isolate...

Page 14: ...cord is furnished The tanks should be on a firm level surface The plug in transformer is for dry locations only Electrical Use a 115 120V 60Hz uninterrupted outlet Batteries are not used 1 The distan...

Page 15: ...th the drain connection on the control valve This will provide an adequate anti siphon trap Where the drain empties into an overhead sewer line a sink type trap must be used Run drain tube to its disc...

Page 16: ...ll be called for on that day even if sufficient number of gallons were not used to call for a regeneration Set Day Override using or buttons number of days between regeneration 1 to 28 or oFF See Sett...

Page 17: ...lay shows the current treated water ow rate through the system The fourth display shows the total amount of treated water from 1x1000 to 9999x1000 gallons This is resettable by simultaneously pressing...

Page 18: ...t the system will regenerate at the preset delayed regeneration time If you pressed the REGEN button in error pressing the button again will cancel the request Note If the regeneration time option is...

Page 19: ...f an extended power outage occurs the time of day will ash on and off which indicates the time of day should be reset The system will remember the rest ERROR MESSAGE If the word ERROR and a number are...

Page 20: ...ily to the drain without the presence of air restore power and momentarily press the REGEN button to advance the control to the BRINE position 5 Fully open the inlet bypass valve handle bypass is now...

Page 21: ...2 sets of dry contacts for user applications The wiring of these contacts is application speci c Relay Speci cations To insure proper t and correct operation the following relay and relay socket manu...

Page 22: ...ck Assembly 1 2 V3004 Drive Cap ASY 1 3 V3372 WS1MR Drive Back Plate 1 4a V3011 WS1 Piston Down ow ASY 1 4b V3011 01 WS1 Piston Up ow ASY 5 V3174 WS1 Regenerant Piston 1 6 V3135 O ring 228 1 7 V3180 O...

Page 23: ...22 REPLACEMENT PARTS...

Page 24: ...23 REPLACEMENT PARTS...

Page 25: ...24 REPLACEMENT PARTS...

Page 26: ...25 REPLACEMENT PARTS...

Page 27: ...26 INSTALLATION FITTING ASSEMBLIES...

Page 28: ...27 WS1 IDENTIFICATION FIGURE WS1 WITH 1 050 DISTRIBUTOR TUBE OPENING IDENTIFICATION...

Page 29: ...et time of regeneration d Control set at on 0 d Check with regen time option in programming e Control set at NORMAL on 0 e Check with regen time option in programming 5 ERROR followed by a code number...

Page 30: ...gged a Connect transformer and PC board power b No power at outlet b Restore power c Broken drive gear of drive cap assembly c Replace gear or drive cap assembly d Defective PC board d Replace board 8...

Page 31: ...431 HURONIA RD UNIT 8 BARRIE ONTARIO L4N 9B3 www waterdepotinc com...

Reviews: