Using Wallbox installation-kit
Structural engineering work must be carried out in accordance 
with current regulations and as specified below:

•  The concrete used for the foundation must be a standard 

ready-mix concrete and be resistant to frost.

•  The charger must be fixed to the ground and be perfectly level. In fact, if 

the charging point leaves a gap from the ground (by lifting the right, left, 
front or rear), it could damage the permeability of the Supernova.

•  It will be necessary to level the system without the use of washers or 

other objects that do not guarantee integral and continuous contact 
between the base of the charging point and the ground.

•  To ensure the optimal installation and the durability of the Supernova, 

use the foundation kit (template and concrete base).

•  To perform the electrical connection, make sure not to cut the tube at the sole 

level to avoid the water penetrating into the charger in case of rain. 

Civil Works

MECHANICAL INSTALLATION

Assembly

Part

Size

Quantity

Tools recommended

Foundation

Foundation

Foundation

Level Plate  
Supernova

DIN 976-1 B

NUT DIN 934

360x701 mm

M16 x 500 mm

M16

2

4

16

Not Applicable

Not Applicable

2x Spanner (size 24 mm)

Material

Steps

To open the right side door, press the 
buttons placed inside of Supernova.

5.

L1 L2

L3 N

L1 L2

L3 N PE

PE

REMEMBER  
When closing the door, apply equal pressure on the upper, middle 
and bottom to ensure that the buttons close correctly.

To close the charger, start from the right doors. Then, close the front 
door and finally lock the door on the left side by using the key.

Door and Keys Instructions

PRODUCT DESCRIPTION AND SITE PREPARATION

Summary of Contents for Supernova

Page 1: ...Supernova INSTALLATION MANUAL...

Page 2: ...ed Tools 15 TRANSPORT AND UNPACKING 16 Transport 16 Unpacking 17 PRODUCT DESCRIPTION AND SITE PREPARATION 20 External view 20 Internal view 21 Site Space Requirements 22 Cable Reach 23 Table of conten...

Page 3: ...ractable system 1 Weight Storage Temperature Operational Noise Level Humidity Operating Temperature Power Balancing Power Split Cooling System Charging Compliance Safety Compliance Cybersecurity Compl...

Page 4: ...GERS S L U All rights reserved Copyright Nameplate Depending on the configuration of the charging station a nameplate will be located on the device Manufacturer Contact and Information GETTING STARTED...

Page 5: ...main service power from the charger before cleaning the unit Do not use cleaning solvents to clean any part of the charger Clean it with a clean dry cloth to remove dust and dirt accumulation Use the...

Page 6: ...ee Electromagnetic compatibility EMC classification EV supply equipment connection Charging Mode Intended Use Fixed parts Floor Standing Assembly Stationary equipment mounted on concrete Indoor and ou...

Page 7: ...d ear injuries Workers need to be very careful when at risk C Heavy object risk of injurious strains Take into consideration that the components of Supernova can be very heavy Be careful when lifting...

Page 8: ...x7 H Washer M16 x2 K Support Entry Plate L Membrane Entry Plate x5 Required Tools GETTING STARTED The following tools required for the installation of Supernova are recommended for the Supernovas ins...

Page 9: ...ot to damage the charging point IMPORTANT Make sure that the charger is stable on the forklift before moving it Supernova can be transported also with a crane In this specific case remove the external...

Page 10: ...harger L1 L2 L3 L4 L1 L2 L3 N PE PE Unpacking TRANSPORT AND UNPACKING 5 L1 L2 L3 L4 L1 L2 L3 N PE PE Unpack the EV guns and plug them in the holsters Then unpack the installation kit 6 Carefully lift...

Page 11: ...cess Key Lock Air intake Product Label Equivalet for EV Cable 2 is located on the other side The images below show the different connections of the divide from the outside Internal view PRODUCT DESCRI...

Page 12: ...cilitate possible maintenance operations The image below shows the recommended minimum distance needed to perform the installation 64 cm 38 cm 38 cm 38 cm Cable Reach PRODUCT DESCRIPTION AND SITE PREP...

Page 13: ...4 L1 L2 L3 N PE PE Introduction L1 L2 L3 L4 L1 L2 L3 N PE PE L1 L2 L3 N L1 L2 L3 N PE PE L1 L2 L3 L4 L1 L2 L3 N PE PE Door and Keys Instructions PRODUCT DESCRIPTION AND SITE PREPARATION 2 1 4 3 L1 L2...

Page 14: ...f the Supernova use the foundation kit template and concrete base To perform the electrical connection make sure not to cut the tube at the sole level to avoid the water penetrating into the charger i...

Page 15: ...ling the base Civil Works MECHANICAL INSTALLATION 1 2 Dig a hole respecting the minimum dimensions of the template It is recommended to leave an extra volume around the template The resulting depth sh...

Page 16: ...lean the excess of the product with some cardboard to spread it around 6 Let the product dry completely 7 At this point place the upper plate and place the charger using a forklift or a crane in corre...

Page 17: ...it above the four rods that protrude from the ground 4 Close only the side door to facilitate the process IMPORTANT Close the doors carefully pushing them steadily to make sure that the electrical co...

Page 18: ...L3 N L1 L2 L3 N PE PE L1 L2 L3 N L1 L2 L3 N PE PE Grid Connection ELECTRICAL INSTALLATION Assembly Part Size Quantity Tools recommended Electrical Cabinet 5 Screws M8 5 Hexagon socket wrench for M8 Ma...

Page 19: ...irement in the data sheet L1 L2 L3 N L1 L2 L3 N PE PE Grid Connection ELECTRICAL INSTALLATION 5 Screw the crimped terminals to L1 L2 L3 N and PE 6 Before closing the electrical protection ensure that...

Page 20: ...vervoltage protection of 20 Vn Nominal Voltage will be necessary The dimensions of the wiring must comply with the regulations and standards in force in the country of installation To calculate the mi...

Page 21: ...nal screws on the sides of the Foot Covers Safety Torx for M6 REMEMBER The concrete shall never exceed the upper level plate to ensure that Supernova anchors on a flat surface Close all doors carefull...

Page 22: ...42 43...

Page 23: ...support wallbox com V 1 0...

Reviews: