Cold weather start-up
Prerequisites
Before starting the generator in cold weather make sure that:
the battery is at peak power
the correct weight motor oil is being used
the starter motor is in good condition
During
operation
The cold starting aid will automatically activate when the air temperature is low
enough. The ECM will notify you that a preheat is in effect.
2.26
Lifting
Prerequisites
Before lifting the generator:
refer to the Technical Data section for the proper operating weight of the
generator
make sure the lifting devices have sufficient capacity to lift the machine safely
make sure the winch or crane to be used for lifting the machine is in operable
condition and designed for such work
Lifting the
generator
A central lifting eye is located at the top of the generator and is attached to a lifting
frame inside the housing.
When lifting the generator, attach a hook or sling securely to the lifting eye.
2.27
Overnight storage
When storing the generator overnight, make sure all access doors are closed and
padlocked.
Do not store the generator overnight in a low lying area that might fill with water
during a heavy storm.
2.28
Long-term storage
If the generator is being stored for several months, follow the engine
manufacturer’s recommendations for long-term storage. These procedures are
designed to help minimize engine corrosion.
Summary of Contents for G 150
Page 1: ...Mobile Generator G 150 G 180 G 240 OPERATOR S MANUAL 0171953en 003 0709 0 1 7 1 9 5 3 E N ...
Page 2: ......
Page 4: ...Foreword G 150 180 240 wc_tx000869gb fm 4 ...
Page 12: ...Safety Information G 150 180 240 wc_si000265gb fm 12 wc_si000265gb fm 12 1 6 Label Locations ...
Page 13: ...G 150 180 240 Safety Information wc_si000265gb fm 13 wc_gr005517 G H J R GG FF R A H K ...
Page 63: ...Factory Installed Options wc_tx000880gb fm 63 Notes ...