Operation
G 150 / 180 / 240
wc_tx000867gb.fm
24
2.3
Normal Boot-up Sequence
During the boot-up sequence, the ECM scrolls through several screens before it
settles into displaying the run screen.
ECM Display
Description
Start of the boot-up sequence. The
ECM display reads “Initializing” and
shows the model of the generator. If
the model displayed does not match
the model of the generator, call
Wacker Neuson Service.
The ECM displays the countdown time
until the next scheduled service. The
timer starts at 250 and counts down to
0.
The ECM displays this screen to
indicate that the intake air is being
heated.
The ECM displays this screen to
signal that the intake air heating
process is complete.
The ECM displays this screen as soon
as the engine starts. Note that some of
the values such as voltage, may not
be up to their running values at this
stage of the sequence.
The ECM displays this screen to let
the operator know that the Under
Frequency Protection system (engine
speed) has been enabled.
Initializing
G xxx
Time to Service
250
Air Intake Heater
0 95% 89 13.9
Return to OFF
0 95% 89 13.9
80 P2 0 60.0
71 75% 87 12.7
Under Frequency
Protect Enabled
Summary of Contents for G 150
Page 1: ...Mobile Generator G 150 G 180 G 240 OPERATOR S MANUAL 0171953en 003 0709 0 1 7 1 9 5 3 E N ...
Page 2: ......
Page 4: ...Foreword G 150 180 240 wc_tx000869gb fm 4 ...
Page 12: ...Safety Information G 150 180 240 wc_si000265gb fm 12 wc_si000265gb fm 12 1 6 Label Locations ...
Page 13: ...G 150 180 240 Safety Information wc_si000265gb fm 13 wc_gr005517 G H J R GG FF R A H K ...
Page 63: ...Factory Installed Options wc_tx000880gb fm 63 Notes ...