28
2.1.3 Stone facing assembly (for stone-faced EH only).
2.1.3.1 Attention! Before the stone facing assembly, connect the Electric heater to the electric mains
and water supply system according to 2.1.1 and 2.1.2 hereof. Install the heater in its operation location.
A diagram of the stone facing assembly is given in Fig. 9.
2.1.3.2 Unpack and sort stone tiles by their lengths (no. 12, Fig. 9) and metal inserts (no. 10 and 11,
Fig. 9) for the front and side EH panels.
2.1.3.3 Remove the top cover (no. 2, Fig. 9). For this, loose 4 self-tapping screws on corner cover ends.
Unscrew the plug (no. 5, Fig. 9) and the decorative nut (no. 6, Fig. 9), then unscrew the steam bleeding
nipple (no. 7, Fig. 9). Remove screws from side handles (no. 4, Fig. 9, Fig. 10). Loose fastening nuts
(no. 8, Fig. 9, Fig. 10) of the front (no. 9, Fig. 9) and side (no. 3 Fig. 9, Fig. 10) panels inside the corners
of the EH case. Pull the side and front panels upwards to remove them.
2.1.3.4 Install metal inserts with protrusions (no. 10, Fig. 9) on the foundation plate (no. 1, Fig. 9) and
align protruding parts of the inserts with plate cutouts. Install first-row stone tiles (no. 12, Fig. 9)
on all three sides by putting on tile cutouts on the inserts (no. 10, Fig. 9). Put metal inserts (no. 11,
Fig. 9) into the cutouts of the installed tiles and install the second row of the tiles. The following rows
of the stone tiles are installed in a similar manner. After the installation of the last (top) row of the tiles,
metal inserts with protrusions (no. 10, Fig. 9) are put into their cutouts. Layouts of the installation of
decorative stone tiles are shown in Fig. 11.
Summary of Contents for PARiZHAR