10
5) Position the slide on the deck such that the slide meets the requirements as given in the
Manufacturer’s Placement Instructions on page 31. Make sure that the slide parts are correctly
positioned on the branch arms. It is recommended that bolts be placed temporarily through the
runway parts and into the first and second branch arms to ensure proper alignment. Once the
assembly is in the correct position, mark the locations for exit support anchors. In addition, make
reference marks at the corners of the main tube support flange to ensure that it remains in the
desired position. Remove the flume sections and drill the anchor holes for both the Main Support (5)
and the Exit Support (6). Drill the two 3/8” diameter X 2” deep holes in the marked locations for the
exit support. The holes in the main support tube flange may be used as a template for drilling the
1/2” diameter X 2-1/4“deep holes. Follow the instruction on page 23 and install the concrete wedge
anchors for the exit support and the main tube support.
6) Place the assembled Exit Flume (3) and Runway Section (2) over the first Branch
Arm (6). Attach the slide sections to the first branch arm as shown above. The required hardware
is as follows: 3/8”-16 x 5.5” Hex Head Cap Screw (8), 3/8” Flat Washer (21), 3/8” Nylon Washer
(23), 3/8” Flat Washer (21), 3/8” Lock Washer (25), and a 3/8” Hex Nut (26). Do not completely
tighten the hardware at this point.
Note: Be sure to apply anti-seize to all fasteners to prevent galling.
MARK LOCATION OF HOLES IN
EXIT SUPPORT FOR DRILLING 3/8”
X 2” DEEP HOLES FOR CONCRETE
ANCHORS
USE HOLES IN FLANGE AS
TEMPLATE FOR DRILLING 1/2”
DIAMETER X 2.25” DEEP HOLES
FOR CONCRETE ANCHORS
FIGURE 8
FIGURE 9
(8)
(23)
(26)
(25)
(21)