Foundation Layout
! CAUTION !
The approximate machine operating weight is 3,000 pounds.
! CAUTION !
The machine foundation should be constructed from concrete or similar material in accordance with
all local and federal OSHA codes and building regulations. The minimum required foundation size
is shown in Figure 3-1. The foundations height will vary depending on the auxiliary equipment
selected by the customer to transport ice to a bin or hopper. Adequate space should be allowed for
removal of the water tank and servicing operations such as cleaning the water distributors.
Figure 3-1 indicates minimum mounting requirements. Contact your local distributor for seismic
anchoring requirements in your area. Additional bracing may need to be added to the top of the
machine mounted to the lifting lug to meet local codes.
Piping and Drain Connections
Figure 3-1 (Water Connections and Refrigerant Connections) shows locations and sizes for all
connections on lowside.
! CAUTION !
External shut-off valves must be provided in the water inlet lines.
The minimum inlet water pressure for satisfactory operation of the machine is 30 psig.
The maximum allowable pressure is 100 psig.
! CAUTION !
Make-up
Water In
Water Tank
Drain*
Water Tank
Overflow
Water Tank
Flush Valve
Suction
Connection
**
Liquid
Connection***
Thaw Gas
Connection***
1/2” FPT
1” FPT
2” FPT
3/4” FPT
2” Flange
3/4” Flange
1 1/4” Flange
*
The water tank drain connection must be extended to an open drain or sump, arranged for visible discharge.
**
Mating 4 bolt flange supplied with machine.
***
Mating 2 bolt flange supplied with machine.
TABLE 3-1
Water Supply and Drain Sizes
! CAUTION !
These lines must NOT be connected into a pressure tight common header
due to the possibility that warm condenser water may back up into the water tank.
The condenser water outlet MUST be piped separately to the drain.
! CAUTION !
Summary of Contents for P18AL TUBE-ICE
Page 1: ...8 28 00 P18AL TUBE ICE MACHINE Manual Part Number 12A4171M09 Service Manual 5000 ...
Page 4: ......
Page 14: ...P18AL Service Manual INTRODUCTION 3 6 07 1 4 FIGURE 1 1 P18AL Front View ...
Page 15: ...P18AL Service Manual INTRODUCTION 3 6 07 1 5 FIGURE 1 2 P18AL Back View ...
Page 16: ...P18AL Service Manual INTRODUCTION 3 6 07 1 6 FIGURE 1 3 P18AL Left View ...
Page 17: ...P18AL Service Manual INTRODUCTION 3 6 07 1 7 FIGURE 1 4 P18AL Right View ...
Page 18: ...P18AL Service Manual INTRODUCTION 3 6 07 1 8 ...
Page 48: ...P18AL Service Manual ELECTRICAL CONTROLS 3 6 07 6 6 ...
Page 56: ...P18AL Service Manual MAINTENANCE 3 6 07 7 8 ...
Page 64: ...P18AL Service Manual TROUBLESHOOTING 3 6 07 8 8 ...
Page 76: ...P18AL Service Manual SERVICE OPERATIONS 3 6 07 9 12 FIGURE 9 3 Cutter Water Tank Assembly ...
Page 78: ...P18AL Service Manual TABLES CHARTS 3 6 07 10 1 10 Tables Charts ...