background image

INSTALLATION OF SHOWER TRAYS

Installation of Shower Trays with Panels

5

1-  The shower tray should be installed to a structurally prepared floor.
 

Temporarily place the shower tray at the installation area. Remove the protective folio of the shower tray from its sides that are touching the wall 
and from the area around the siphon. The remaining protective folio on the shower tray should be removed only after the shower tray installation 
and other construction works in the bathroom are finished. 

2-  If the shower tray is purchased with a packaging on pallets, the leg sets must be installed to the shower tray. In this case the leg profiles are 

prepared to be installed on the shower tray. The shower tray is placed upside down on a clean floor and the U shaped legs are inserted to the 
toggle and fixed to the bottom of the product via two screws. If the shower tray’s legs are new profile legs then the New Profile Leg Installation 
steps should be followed.

3-  Adjust and level the leg set according to the height of the panel. Check the evenness with a scale. (See the Technical Data Sheet for the panel 

height). 

4-  Tighten the let sets nuts.

5-  The floor tiles are marked through the holes in the leg set’s plastic feet. Caution! Where wall hangers are used there’s no need to fix the legs of 

the shower tray to the floor. However if there are un level walls the leg installation holes for the shower trays are drilled with a 7-8 tip drill. Caution! 
No hole should be drilled on heated and isolated floors.

6-  The points on the wall tiles are marked for installing the wall hangers. (The spots shown with “A” in in the "Plan” section of the Technical Data 

Sheet).

7-  The shower trays is removed from its location. The spots marked on the wall are drilled with a tip 10 drill (and if required, the spots marked on 

the floor are drilled with a tip 7-8 drill), the pegs are inserted in the holes and the wall hangers are installed. (The spots shown as “Wall Hanger 
Detail” in the Technical Data Sheet).   

8-  The siphon outlet connection is supported with silicone.

9-  The prepared siphon is installed. (At this stage do not forget to remove protective folio on the shower tray around the siphon hole.) After the 

siphon outlet is connected it is checked for leak proof ness.

10-  The legs of the shower tray are screwed to the floor. However, as mentioned above, if wall hangers are used there’s no need to fix the legs of the 

shower tray to the floor. The legs of the shower tray are fixed to the floor if there are un-level walls. (Caution! No hole should be drilled on heated 
and isolated floors).

11-  The shower tray is fixed to the wall using the wall hangers. (Technical details are shown as “Wall Hanger Detail” in the Technical Data Sheet).
12-  The protective folios of the panels are removed.

Points that Require Attention:

•  Because of the technical properties of the products, the installation of shower trays were classified into four methods and explained in the 

following order:

  1. Installation of Shower Trays with Panels
  2. Installation of Monoblock Shower Trays
  3. Installation of Flat Shower Trays and Shower Trays for the Disabled
  4. Installation of Zero Surface Shower Trays
•  For the technical details of shower trays, the technical data sheets should be consulted.
•  Before installation it should be checked that the floor tiles are even and the walls are 90°C at the installation location.
•  We recommend to install shower trays with panels and monoblock shower trays only after tiling the wall tiles and completing all construction 

work in the bathroom.

•  The installation of flat and zero surface shower trays should be performed before or during tiling
•  Cold and hot water connections must be already realized.

Summary of Contents for ACRYLIC SHOWER TRAYS

Page 1: ...ACRYLIC SHOWER TRAYS Installation and User Manual ...

Page 2: ...ms You May Encounter and Their Solutions 10 Cleaning of Acrylic Shower Trays 10 Usage of Shower Tray Siphon Key 10 Matters Not Covered Under Warranty 11 Transportation Storage 11 Installation 11 Use Cleaning and Maintenance 11 October 2016 www vitra com tr This user manual applies to all VitrA Acrylic Shower Tray Models Manufacturer Company Eczacıbaşı Yapı Gereçleri San ve Tic A Ş Șekerpınarı Cumh...

Page 3: ...rom our seller for the telephone number of the Authorized Service in the area you are living in In places where we do not have a seller you may get the necessary information from the telephone numbers given in the guide Ask the service personnel to display their Vitra Artema Authorized Service Personnel Card Do not let people without a personnel card perform the installation At the completion of t...

Page 4: ...res are completed GENERAL CHARACTERISTICS OF THE PRODUCT The highest quality polymethylacrylate in other words Acrylic is used as the primary material in the production of VitrA Acrylic Shower Trays Acrylic which has a high wear resistance is preferred because it can be easily cleaned and does not host microorganisms Acrylic is known to be one of most accommodating materials for human nature Havin...

Page 5: ...illed with a tip 10 drill and if required the spots marked on the floor are drilled with a tip 7 8 drill the pegs are inserted in the holes and the wall hangers are installed The spots shown as Wall Hanger Detail in the Technical Data Sheet 8 The siphon outlet connection is supported with silicone 9 The prepared siphon is installed At this stage do not forget to remove protective folio on the showe...

Page 6: ... the low floor grounding where the shower tray will be seated into with a mixture of cement and humid sand up to the flooring level without covering the siphon The purpose of this application is to fill with cement and sand mixture in order to prevent any flexing of the shower tray 6 Support the siphon seal with silicone 7 Place the shower tray in the installation area Make the siphon filter connection...

Page 7: ...the leg to the product using the 25 mm screws provided with the leg set through the two screw holes 5 Fixate the support shaft by tightening it the two nuts so that it will press on the edge frame of the product 6 Adjust the height of the plastic feet according to the height of the panel 7 Fixate the plastic feet which you ve adjusted by tightening the two nuts 8 Fixate the middle feet of the show...

Page 8: ...th the shower tray and the wall 7 The installation of the monoblock shower tray is complete Any protective folio remaining on the shower tray should be removed only after all of the construction works in the bathroom are finished 5 After the siphon is placed and its connections are carried out fill the low floor grounding where the shower tray will be seated into with a mixture of cement and humid sa...

Page 9: ...to surface shower trays the wall tiles are laid down by leaving a jointing space from the sides of the shower tray 12 When tiling the wall and floor tiles for zero to surface shower trays if the upper edge of the shower tray and the finished floor tiles are required to be level with the floor tiles then floor tiles are laid by leaving a jointing space from the sides of shower tray 13 The installation o...

Page 10: ...ratching cleaning sponges Do not let organic dilutions paint removers acetone and other solvents contact the glass Acrylic is durable against acids and alkalines However do not let organic solutions used in dry cleaning paint remover substances acetone or other solvents to your compact system Keep lighted cigarettes away from the product If the construction activities in the bath will continue aft...

Page 11: ...eakages which may occur as the result of impacts 2 Deformations and breakages on the surfaces of products which remain at the construction site for a long time without protection 3 Damage to the product as the result of effects of the water and or humidity in the environment during the storage and use of the products 4 Products damaged by each other due to stacking on top of each other during stor...

Page 12: ......

Reviews: