Place the converter for the flowthrough regulator on the Easytop cir‐
culation regulation valve to position t.D..
n
Open every extraction fitting fully and flush for at least 3 minutes
after 70 °C has been reached.
n
Place the flowthrough regulator and ball valve in the operating posi‐
tion.
n
Do exactly the same with all of the circulation circuits.
NOTICE!
Thermal disinfection be can carried out automatically in
combination with a building management system (on-site)
and the Easytop actuator set model 1013.9. Manual adjust‐
ment of the valve is no longer necessary.
3.2.7
Leakage test
The installer must perform a leakage test before commissioning.
Carry out this test on a system that is finished but not covered yet.
Comply with the general rules of engineering and the applicable direc‐
tives, see
„Regulations from section: Leakage test“ on page 8
Document the result.
3.3
Maintenance
NOTICE!
Inform your customer or the operator of the potable water
installation that the system has to be maintained on a reg‐
ular basis.
Observe the applicable regulations for the operation and maintenance
of potable water installations, see
„Regulations from section: Mainte‐
3.4
Disposal
Separate the product and packaging materials (e. g. paper, metal,
plastic or non-ferrous metals) and dispose of in accordance with valid
national legal requirements.
Handling
Easytop circulation regulation valve S/E with SC-Contur