background image

PRE-OPERATION CHECKS AND 

ADJUSTMENTS

Every Victaulic pipe stand is checked, adjusted, 
and tested at the factory prior to shipment . The 
pipe stand should be inspected for any damage 
that may have occurred during shipping and 
handling .
Before operating the pipe stand, the following 
checks and adjustments should be made to 
ensure proper pipe stand operation . Repeat 
these steps when the pipe stand is moved and 
when it is transported to an alternate location .

PIPE PREPARATION

Prepare pipe for roll grooving in accordance with 
the Operating and Maintenance Instructions 
Manual for the applicable tool being used to roll 
groove the pipe . In addition, inspect the pipe 
surface for dents or surface build-up where 
contact with the pipe stand’s polyethylene 
wheels will occur . The pipe surface should be 
free of large dents, and free of accumulations 
of dirt, rust, or grime that may interfere with 
smooth pipe rotation .

Pipe with external, axial weld seams can be 
used with the stand . However, the weld bead 
must be smooth and rounded, and must be at 
least three times as wide as it is high . The weld 
bead must not exceed 

1/8

 inch/3 mm in height . 

To minimize wear on the rollers and polyethylene 
wheels, grind the weld bead flush where the 
pipe makes contact with the stand .

NOTICE

•  Grooving pipe that contains external 

weld seams will shorten the life of the 
polyethylene wheels.

TOOL AND PIPE STAND SETUP

1.

  When grooving pipe that is supported with 

a pipe stand, select a location for the tool 
and pipe stand by taking into consideration 
the following factors:

 a.

   Adequate space to handle pipe  

 lengths

 b.

   A firm and level surface for the pipe  

 stand

 c.

   Anchoring requirements for the pipe  

 stand

2.

  Ensure that the roll grooving tool is 

LEVELED

 and 

FASTENED SECURELY

 to a 

concrete floor . Refer to the Operating and 
Maintenance Instructions Manual for the 
applicable tool being used to roll groove 
the pipe .

3.

  Position the stand in an approximate 

operating location, as explained below . 
Always refer to the “Grooving Long Pipe 
Lengths” section in the Operating and 
Maintenance Instructions Manual for the 
applicable tool being used to roll groove 
the pipe .

 a.

  Determine the length of the pipe to  

 

be roll grooved .

 b.

  Position the pipe stand at a distance  

 

slightly greater than half the pipe  

 

length from the tool (half the pipe  

 

length, plus 5%) . 

 c.

  Position the pipe stand approximately  

 

in line with the tool’s grooving rolls or  

 

slightly to the left .

 d.

  Ensure that the base is level, front to  

 back .

9

REV_B

TM-VAPS1672 

/ Operating and Maintenance Instructions Manual

Summary of Contents for VAPS1672

Page 1: ...uctions in this manual and all warning labels on the tool Wear safety glasses hardhat foot protection and hearing protection while working around this tool Save this operating and maintenance manual i...

Page 2: ......

Page 3: ...Nomenclature 7 Tool Dimensions and Specifications 8 Pre Operation Checks and Adjustments 9 Pipe Preparation 9 Tool and Pipe Stand Setup 9 Initial Pipe Stand Adjustments 10 Ratchet Operation 12 Final...

Page 4: ...pipe to be roll grooved These instructions must be read and understood by each operator PRIOR to working with the stand These instructions describe safe operation of the stand including set up and ma...

Page 5: ...stand performance CAUTION 1 The VAPS1672 pipe stand is designed ONLY for supporting pipe sizes materials and wall thicknesses as designated 2 Inspect the equipment Before using the pipe stand check m...

Page 6: ...ailure resulting in property damage or personal injury The VAPS1672 Pipe Stand supports pipe sizes 16 72 inches 406 4 1829 mm 11 2 foot 0 5 meter to full single 20 foot 6 meter random lengths and has...

Page 7: ...the tool Wear safety glasses hardhat foot protection and hearing protection when working around tools 0567 Rev D R031272LAB If you need additional copies of any literature or if you have questions co...

Page 8: ...TOOL DIMENSIONS AND SPECIFICATIONS Net pipe stand weight is 480 pounds 218 kilograms 43 8 in 1113 mm 36 0 in 914 mm 20 0 in 508 mm 8 REV_B TM VAPS1672 Operating and Maintenance Instructions Manual...

Page 9: ...and polyethylene wheels grind the weld bead flush where the pipe makes contact with the stand NOTICE Grooving pipe that contains external weld seams will shorten the life of the polyethylene wheels T...

Page 10: ...lower hole locations as shown above When grooving 48 72 inch 1219 1829 mm pipe sizes The polyethylene wheels must be installed in the upper hole locations as shown above 2 To change locations of the...

Page 11: ...lyethylene wheel 6 Install a flat washer and hex lock nut onto the end of the threaded roll shaft hex nut assembly 7 Tighten the hex lock nut completely to retain the polyethylene wheel 8 Repeat steps...

Page 12: ...middle location when viewed from the end of the ratchet to enable the ratchet to rotate freely In this position the ratchet can be rotated clockwise to raise the roller support or counterclockwise to...

Page 13: ...uctions Manual for the applicable tool being used to roll groove the pipe Follow the steps below to check the test groove for accuracy Adjust and repeat test groove as necessary until the appropriate...

Page 14: ...and raise the roller support 3 On a monthly basis apply chain lubricant to the entire length of the chain 4 Lubricate the threaded roll shaft hex nut assemblies that retain the polyethylene wheels PA...

Page 15: ...ard Pipe is out of specification Pipe face is excessively scuffed Pipe is over tracking Pipe will not stay in roll grooving tool Insufficient pipe tracking angle Pipe is rotating in the wrong directio...

Page 16: ...ICTAULIC IS A REGISTERED TRADEMARK OF VICTAULIC COMPANY AND OR ITS AFFILIATED ENTITIES IN THE UNITED STATES AND OR OTHER COUNTRIES 2018 VICTAULIC COMPANY ALL RIGHTS RESERVED OPERATING AND MAINTENANCE...

Reviews: