Commissioning 

7.1 

Connection to the heating system and filling with water 

Before filling the heating system with water the system should be duly cleaned, it means that the system should be 
twice filled with clean water and drained.  
Water for the boiler and the heating system filling must be clear and colourless, without suspended solids, 
oil and aggressive chemicals. The heating system must be filled with water that meets the requirements of 
CSN 07 7401 and especially its hardness must not exceed the required parameters. 
The parameters of circulating and make-up water must correspond to the following: 
 
Tab. 

. 5 

The maximum permissible values of heating water according to CSN 07 7401 

Recommended values 

Hardness 

mmol/L 

Ca

2+

 

mmol/L 

0.3 

Total Fe + Mn concentration 

mg/L 

(0,3)* 

*recommended value 

ATTENTION!!! The manufacturer does not recommend the use of antifreeze.  

 

If the water hardness is unsuitable it has to be adjusted. Even the multiple heating of water with a higher hardness 
does  not  exclude  salts  on  the  boiler  body  walls.  Precipitation  of  1  mm  calcite  reduces  at  a  given  point  the  heat 
transfer from the metal to water by 10%. 
During  the  heating  season,  it  is  necessary  to  maintain  a  constant  volume  of  heating  water  in  the  heating  system 
and ensure that the heating system is vented. Water from the boiler and the heating system must never be drained 
or  taken  for  usage  except  for  the  emergency  cases  like  repairs  etc.  Heating  water  discharge  and  filling  with  new 
water increases the danger of corrosion and scaling. If it is necessary to refill water in the heating system, refill 
only the cold boiler
 in order to avoid disruption.  
Before  filling  the  system  with  water,  shift  a  three-way  valve  control  lever  into  the  intermediate  position  using  a 
screwdriver  or  manually  by  pulling  it  toward  yourself  slightly  down  (if  the  boiler  has  the  option  of  feeder  water 
preparation) Fig. No. 9. After filling the heating system, dismantle the water valve drive by pushing the metal push 
button and turning right. After remounting the water valve drive, the lever comes back to the position for heating the 
heating system. 
 

Lever shifted in the intermediate 

position when filling the heating 

system and water heater

 

Lever in the position for HW heating 

 

 

Lever in the position for heating the 

heating system

 

 

 

 

 

 

 

 

Fig. 

. 9 

Three-way valve VC 4013 

 
When filling the boiler with water the system must be disconnected from the mains. Bleeder valve on the boiler and 
on the heating system must be open and functional. 

Adjust the expansion vessel to a pressure of 10 kPa 

(0.1 bar) higher than the pressure required in the heating system (only for the version 

CLAUDIUS

 

K 2  L31,  CLAUDIUS

 

K 2  L33).  The  system  is  pressurized  to  the  desired  pressure  of  about  100  kPa  (1  bar)  and 

again vented. For filling water, it is recommended to use a filter on the heating system inlet.  
The heating system must have a sufficient number of vents. Drain valve must be installed at the lowest point of the 
heating system.  
The  expansion  tank  is  8  L  volume  and  its  volume  is  sufficient  for  150  l  of  water  in  the  heating  system.  The 
expansion tank is not mounted for the version CLAUDIUS K 2 L5X.  
The  system  should  be  designed  to  a  temperature  gradient  of  55/45  °C  with  respect  to  condensation  use. 
Condensing boiler can be used also for old self-load systems which were pre-dimensioned and thus condensation 
can  be  efficiently  used  also  for  this  system,  but  the  system  should  be  supplemented  with  a  corresponding 
expansion tank.  

Summary of Contents for CLAUDIUS K 2 Series

Page 1: ...VIADRUS CLAUDIUS K 2 Manual for boiler operation and installation GB_2016_35 GB_2016_43...

Page 2: ...m and filling with water 15 7 2 Gas connection 16 7 3 Connection to the mains 16 7 4 Condensate drain 16 7 5 Flue gas exhaust 16 7 6 Pressure losses of flue gas exhaust components for the boiler VIADR...

Page 3: ...for heating of houses recreation facilities and also for reconstruction of heat sources in individual flats Heat output of the condensing boiler is 3 8 to 24 kW K 2 L3X and 7 8 to 48 1 kW K 2 L5X The...

Page 4: ...condensate outlet mm 25 25 safety valve outlet Js 3 4 3 4 gas inlet Js 3 4 3 4 Supply voltage 1 N PE 230 VAC 50 Hz TN S Input power including pumps W 110 110 El protection IP 41 41 Tab 2 Heat technic...

Page 5: ...temperature mode 4 87 6 At 30 of rated heat output and low temperature regime P1 4 3 kW At 30 of rated heat output and low temperature regime 1 97 6 Consumption of auxiliary electrical power Other it...

Page 6: ...temperature mode 4 87 8 At 30 of rated heat output and low temperature regime P1 8 8 kW At 30 of rated heat output and low temperature regime 1 97 8 Consumption of auxiliary electrical power Other it...

Page 7: ...controlled equithermally it is necessary to connect the outdoor sensor In this case we recommend using one of the communication devices see chap 6 3 To increase the number of heating circuits expansio...

Page 8: ...is equipped with an additional anticorrosive device in the form of a magnesium anode whose function is based on the utilization of the electrochemical potential difference between the anode and the ta...

Page 9: ...entral heating circulation supply return pipeline R 3 4 E socket heating coil R 5 4 Sensor housing R 3 8 Thermometer internal thread 1 2 Water drain 3 4 Magnesium anode An stopper 2 Weight empty kg 57...

Page 10: ...Selection and erection of electrical equipment Common rules CSN 33 2000 7 703 ed 2 Electrical installations of buildings Part 7 703 Requirements for special installations or locations Rooms and cabins...

Page 11: ...ards wood and fibreboards plastics flooring materials the safe distance is doubled it means that the distance is 400 mm The safe distance is to be doubled also in case when the fire reaction class is...

Page 12: ...ng to the project K 2 L3X K 2 L5X L mm 502 587 L1 mm 213 5 293 5 L2 mm 105 5 183 5 V1 mm 426 440 diam D mm 80 110 Fig 6 Rear view of the boiler 1 Heating water outlet from the boiler if a water heater...

Page 13: ...mperature sensor input B9 External temperature sensor B38 HW temperature sensor input BTr Room thermostat E1 Kindling electrode E2 Monitoring electrode MV1 Fan MV1 Fan Q1 Pump X1a Power supply connect...

Page 14: ...ector 230 X1b Three way valve and selected output connector X1f Fan and pump power supply connector X2 Kindling transformer and gas valve connector X4 Temperature sensors and Reset button connector X5...

Page 15: ...ption Before filling the system with water shift a three way valve control lever into the intermediate position using a screwdriver or manually by pulling it toward yourself slightly down if the boile...

Page 16: ...he boiler commissioning check whether the condensate is drained Size of a waste PVC pipe is of 16 mm The condensate pH is 4 5 and it can be drained into the sewer system without treatment The boiler c...

Page 17: ...h a special liner intended for the condensation boiler and a condensate drain from the chimney For the boiler it is possible to use a plastic liner with the temperature resistance of 120 C Version C8...

Page 18: ...d calculation of the relevant flue gas exhaust 7 7 Boiler commissioning The entire installation must comply with regulations related to this equipment The boiler must be compatible with local connecti...

Page 19: ...the flue gas which must be in the range of 8 4 to 8 8 The recommended value is 8 5 7 Wait about 120 seconds until the boiler operation gets stabilized and check or adjust the CO2 max value using the C...

Page 20: ...e selected parameter value A B C H D E F G I J Fig 13 A Operation mode switch FV OFF ON for the HW heating B RESET button burner fault unblocking press for about 3 s C ESC button returning one step ba...

Page 21: ...s 1 Time 00 00 23 59 hh mm 1 Date 01 01 31 12 dd MM 5 Summer time start 25 03 01 01 31 12 dd MM 6 Summer time end 25 10 01 01 31 12 dd MM Current date and time must be set due to the correct function...

Page 22: ...0 00 00 24 00 hh mm 602 Mo Su 1 Phase OFF 22 00 00 00 24 00 hh mm 603 Mo Su 2 Phase ON 24 00 00 00 24 00 hh mm 604 Mo Su 2 Phase OFF 24 00 00 00 24 00 hh mm 605 Mo Su 3 Phase ON 24 00 00 00 24 00 hh m...

Page 23: ...Fig No 18 Summer winter automatic temperature limit for switching between summer and winter mode Req T Run up Room Thermostat the temperature to which the boiler will heat when the outside sensor is n...

Page 24: ...on In case of recurrence of the error contact service 8 5 Faults Fault Reason Solution The boiler does not ignite No voltage at the boiler Check whether the power cord is plugged in and whether there...

Page 25: ...hrough the burner chamber leave for 10 min and rinse with clean water Any impurities will be discharged through a siphon 10 Install the burner plate by means of 4 nuts and washers M6 connect the fan c...

Page 26: ...eriod it is necessary to add to the system a manufacturer approved antifreeze for this type of boiler or drain the system to avoid freezing of the heating system and the boiler For the boilers with fl...

Page 27: ...Performance of regular service inspections within the range specified by the manufacturer by a service company with a valid service certificate For an eventual housing complaint the customer is oblig...

Page 28: ...aging unit EN 13429 NO 3 1 Recovery by material recycling ensure recyclability in all terms of the standard for the functional packaging unit EN 13430 YES 3 2 Recovery in the form of energy ensure tha...

Page 29: ...nty certificate for customer user A record of warranty and after warranty repairs and regular annual product inspections Record date Carried out activity Contracting service organization signature sta...

Page 30: ...30...

Page 31: ...31...

Page 32: ...VIADRUS CLAUDIUS K 2 VIADRUS a s Bezru ova 300 E mail CZ 735 81 Bohum n info viadrus cz www viadrus cz...

Reviews: