3.6 Installing Modules
The Liebert APS ships configured from the factory (modules pre-populated) and tested as a system to
your requirements. If you removed any modules to facilitate installation, refer to the following steps to re-
insert them properly.
3.6.1 Installing Power, Battery and Charger Modules
1. With the plastic bezel removed, lift module to appropriate bay, resting end of module on bay
shelf.
NOTE: Do not rest the module on any plastic bezels. It could damage the bezel.
NOTE: Two battery modules must be installed in the same row to complete the battery string.
2. Refering to Figure 3.9 below, slowly push the module until about 1/3 of the module is in the
bay.
3. Lift the module up, then continue pushing until about 5 cm (2 in.) of the module remains
outside the bay, then push it firmly and smoothly to insure that it is fully inserted.
Figure 3.9 Inserting power, battery and charger modules
ITEM
DESCRIPTION
1
Push in slowly about 1/3 of the module.
2
Lift and push smoothly and firmly until fully inserted.
4. Pull out the lock lever slightly, and press the lever down slightly, see
NOTE: If the lever does not press down smoothly, remove and reinstall the module.
Vertiv
| Liebert® APS™ Installer/User Guide |
29
Summary of Contents for Liebert APS series
Page 1: ...Liebert APS 5 20 kVA Modular UPS Installer User Guide...
Page 6: ...Vertiv Liebert APS Installer User Guide 6...
Page 10: ...Vertiv Liebert APS Installer User Guide 10 This page intentionally left blank...
Page 50: ...Vertiv Liebert APS Installer User Guide 50 This page intentionally left blank...
Page 76: ...Vertiv Liebert APS Installer User Guide 76 This page intentionally left blank...
Page 80: ...Vertiv Liebert APS Installer User Guide 80 This page intentionally left blank...
Page 109: ......