1.
Fix the fastener on one side of the floating nut into the square hole of the crossbeam, as shown in
Figure 3-26
.
2.
Lead the floating nut hook through the square hole to fasten the fastener on the other side of the floating nut, and
gently rotate the floating nut hook to make the fastener totally fixed into the square hole, as shown in
Figure 3-27
.
Figure 3-27 Floating Nut Mounting
•
The floating nut should be inserted into the square hole in level direction, that is, the fasteners on both
sides of the floating nuts should touch the left and right sides of the square hole. Do not make the fasteners
touch the top and bottom sides of the square hole.
The removal steps for floating nuts are as follows:
1.
Remove the screws mounted on the floating nut.
2.
Squeeze the sides of the floating nut by hand to remove it from the square hole.
3.13.
Fixing the Rack on the Floor
There are two groups of reserved installation holes on the frame of the bottom rack, four for each group, as shown
in
Figure 3-28
. These holes are used to fix the rack on the floor. Lead M8 screws through the four reserved
installation holes on the frame from inside of the rack to fix the rack on the floor.
If you need to strengthen the fixation between the rack and the floor, remove the feet referring to section
“3.10.
Removing the Feet and Caster (optional)”
. Lead M12 screws through the M12 installation holes, which will appear
after removing the feet, from underside of the rack to fix the rack on the floor.