36 Chapter 4 Commissioning Instructions
SmartCabinet Series Solution Product for IDC or Computer Rooms User Manual
Chapter 4 Commissioning Instructions
This chapter introduces the operation instructions of SmartCabinet, including check before startup, and procedures of
power on and power off and system commissioning.
4.1 Commissioning Procedures
The commissioning procedures of SmartCabinet are as shown in Figure 4-1.
Figure 4-1 Commissioning flow chart
4.2 Preparations
The product commissioning is used to support the product deployment. Prior to the commissioning, the device status
should meet the following conditions:
The hardware installation and inspection work have been done, and the cabling work and inspection are completed
correctly.
4.3 Inspection
Prior to starting up the SmartCabinet cabinet, you need to perform the following inspections:
Table 4-1 Checklist
Inspection items
Inspection criteria
Remark
Distribution
Check and measure and confirm if the AC mains voltage and frequency are normal, and
confirm if the AC mains connection is correct without short circuit.
Check and confirm if the distribution cables of UPS and PMU are correct without short
circuit.
Check if the battery (if configured) installation and wiring are correct, and check if the
battery positive and negative polarities are correct.
Monitoring unit
Check if the all the communication network cables are connected in correct sequence
according to the wiring diagram and cable No.
Thermal
management
system
Check if the air conditioner is charged with refrigerants.
Check if the air conditioner pipes are normally connected without leakage.
Check if the emergent fan power supply port is correct.
Intelligent lock
Check if the distribution and signal cables of the intelligent lock are correct according to
the wiring diagram and cable No.
Optional
Check and confirm if the access control card can normally open the intelligent lock
Check the fire
fighting
Check and confirm the fire protection system stem node is normal access.
Optional
System
Check if the vacant space has been sealed by dummy plates.
Start
Prepare
Inspection
Startup and
Commissioning
Shutdown
System
Commissioning
End