6 Commissioning

uniSTOR GB

20

6.2 Filling the Primary Circuit

Note:
Do not use boiler pressure relief valve for
venting purposes.

The complete primary CH system must be flushed out
with both cold and hot water. Fill and vent the central
heating system as detailed in the boiler installation
instructions.
To assist with this operation set the manual override
lever on the 2 port diverter valve (fig. 7) to the
MANUAL position, and lock in this position by pushing
the lever into the valve head.

Completely drain the CH system, then refill and vent.

Reset the lever on the 2 port valve to the ”AUTO”
position by releasing the manual operating lever from
the valve head (pull outwards). 
For commissioning purposes and to reduce the time
for the cylinder contents to reach temperature, set the
cylinder hot water thermostat knob (1, fig. 14) to
setting middle position (approx. 40 °C).

Fig. 14 Electrical Connections to Cylinder Controls

Operate the boiler as in section 6.3 until both the
cylinder has reached temperature and all radiators in
the system are hot. Then once again drain the
complete CH system to remove residues from the
pipework and refill and vent again as above.

Reset the manual operating lever on the 2 port valve
to the ”AUTO” position once the system has been
refilled and vented.

1

1

2

3

N

L

immer

sion

he
at

er

c

ylinder

co

n

tr

ol

6 Commissioning

6.1 Filling Secondary DHW Circuit

Note:
Do not manually open the temperature and
pressure relief valve or expansion relief valve for
venting purposes (any foreign matter in the
pipework may cause damage to the valve seats).

Ensure that the cylinder drain valve (9, fig. 6) is
closed.

Open all the hot and cold water taps or other terminal
fittings.

Open the mains water supply to the uniSTOR and
continue filling until water runs freely from the
terminal fittings, ensuring all air pockets are purged.

• Close the terminal fittings and check the system for

leaks. Specially check the connection of the immersion
heater for leaks.

The system should now be thoroughly flushed.

Open hot water taps at opposite ends of the system
and allow water to discharge for at least 5 minutes.

Close the hot water taps.

0020005468_02_GB_042008.qxd  16.04.2008  14:17 Uhr  Seite 20

Summary of Contents for uniSTOR VIH GB SERIES

Page 1: ...Instructions for Installation and Use uniSTOR Unvented hot water storage cylinder VIH GB 125 S VIH GB 155 S VIH GB 180 S VIH GB 210 S VIH GB 260 S VIH GB 310 S GB...

Page 2: ...y System 8 4 2 Secondary Return 8 5 Installation 9 5 1 Installation requirements 9 5 1 1 Siting 9 5 1 2 Mains Water Pressure 9 5 1 3 Pipework Primary Circuit 9 5 1 4 Discharge Pipework 9 5 1 4 1 High...

Page 3: ...ting is controlled by a separatly fitted 2 port valve in conjunction with suitable external controls such as a programmer room thermostat or thermostatic radiator valves 1 3 Immersion Heater uniSTOR c...

Page 4: ...28 30 33 39 44 49 kg Weight full 145 175 205 245 310 340 kg Height 969 1179 1339 1499 1789 2109 mm Cylinder connections Cold mains inlet 22 mm compression DHW outlet 22 mm compression Balanced pressu...

Page 5: ...ate cylinder heat up time 15 C to 65 C minutes Reheat time for 70 of cylinder contents minutes 50 40 10 20 30 40 60 50 30 20 12 Heat input to cylinder kW Cylinder Heat Up Times 15 20 25 30 38 35 VIH G...

Page 6: ...d be completed by the installer and or commissioning engineer and handed to the user All CORGI registered installers carry a CORGI ID card and have a registration number Both should be recorded in you...

Page 7: ...y will become invalid if the damage is due to frost or freezing transient voltages lightning strikes or any act of vandalism or misuse 2 The proof of purchase must be produced in the event of any warr...

Page 8: ...aws of the local Water Undertaking The installation is subject to Building Regulation approval notify the Local Authority of intention to install In the event of parts replacement use only genuine spa...

Page 9: ...uniSTOR unvented storage cylinder should not be installed Contact Vaillant Ltd for details on alternative hot water supply systems In order to minimise frictional losses minimum 22 mm bore is recomme...

Page 10: ...g temperature relief valve 500 mm maximum 300 mm minimum providing that where children may play or otherwise come into contact with discharges a wire cage or similar guard is positioned to prevent co...

Page 11: ...84 314 589 903 VIH GB 180 S 1308 1339 454 384 314 589 1038 VIH GB 210 S 1468 1499 454 384 314 589 1118 VIH GB 260 S 1758 1789 454 384 314 589 1408 1376 VIH GB 310 S 2078 2109 454 384 314 589 1648 1376...

Page 12: ...niSTOR GB 12 1 Boiler 2 uniSTOR cylinder 3 2 port motorised valve provided with the boiler 4 Immersion heater 5 2 port motorised valve A Boiler flow B Boiler return Fig 5 1 A B 2 4 3 5 M M DHW 5 3 Fun...

Page 13: ...f valve 2 Expansion relief valve 3 Pressure limiting valve combined with strainer 4 Connection to expansion vessel 5 Balanced pressure cold water outlet 6 Cold water mains inlet 7 DHW outlet 8 Tundish...

Page 14: ...ns supply to the uniSTOR To ensure optimum performance from the uniSTOR and particularly in installations where the balanced pressure cold water outlet 5 fig 8 is to be used the pipework provided from...

Page 15: ...pe runs are of excessive length or there are several terminal fittings supplied extend the length of pipework in 22 mm Connect the secondary return if required as shown in 4 2 Secondary Return 5 4 3 S...

Page 16: ...ls 1 Thermostat adjustable b Immersion heater 2 Thermal cut out with Reset button 3 Sensor 2 1 2 a b 1 3 230 V AC 3 kW 1 2 3 N L Important The immersion heater incorporates an energy cut off device an...

Page 17: ...for electrical installations IEE Wiring Regulations 16th edition Check that the sensors from the immersion heater and the cylinder are positioned correctly in the tubes Note A special accessory is off...

Page 18: ...Note Earth not required Link L 2 5 Siemens Landis Staefa RWB2 RWB9 Potterton Myson EP 2002 EP 3002 EP 6002 Note Link L 5 Sunvic Select 207 N L 2 3 4 5 3 7 6 1 E N L 2 3 4 1 E N L 2 3 4 5 3 7 6 1 N 3 5...

Page 19: ...4 5 6 7 8 9 10 SL 1 2 3 uniSTOR VIH GB Central Heating 2 Port Motorised Valve Hot Water 2 Port Motorised Valve Cylinder Stat E BL BR GR OR L N Pump E BL BR GR OR L N HW ON CH ON 2 Channel Programmer...

Page 20: ...cylinder has reached temperature and all radiators in the system are hot Then once again drain the complete CH system to remove residues from the pipework and refill and vent again as above Reset the...

Page 21: ...ring frost conditions Advise the user that the immersion heater is provided as a back up means of water heating and is not intended for use at the same time that the boiler is heating the cylinder Fin...

Page 22: ...g to controls instructions Is 2 port valve in correct position DHW position Does cylinder thermostat operate Replace cylinder thermostat Vent heating coil of air H fig 4 Check replace 2 port valve Is...

Page 23: ...ansion vessel Does pressure hold Turn off boiler and immersion heater Is discharge still occuring YES NOT OK Is the discharge occuring only when the cylinder is being heated YES NO Is pressure downstr...

Page 24: ...ty YES Replace TPRV Replace immersion heater NO YES NO Is operation now OK OK Fault remedied NOT OK Check temperature control of boiler Does 2 port valve change to heating position when cylinder reach...

Page 25: ...limiting valve OK Check pressure limiting valve OK Check sytem for blockage OK Symptoms still persisting YES Check system as for discharge from temperature or expansion relief valve Inform customer t...

Page 26: ......

Page 27: ......

Page 28: ...0020005468_02 GB 042008 Subject to alteration Printed in Germany...

Reviews: