5 Installation
10
Installation and maintenance instructions aroCOLLECT 0020217119_01
ca. 0,5 m
≥ 0,3 m
≥ 0,5 m
≥ 0,5 m
≤ 5 m
≥ 3 m
≥ 0,5 m
< +5 °C
< +5 °C
≥
0,5 m
Clearances that must be complied with for two air/brine col-
lectors
Positioning of the collectors
▶
Use the mounting base, which is available as an access-
ory, for the installation.
▶
To guarantee sufficient air flow and to facilitate mainten-
ance work, observe the minimum clearances that are
specified above.
▶
Ensure that there is sufficient room to install the hydraulic
lines.
▶
If the product is to be installed in areas where heavy
snow falls, ensure that the snow does not accumulate
around the product and that the minimum clearances
specified above are observed. If you cannot ensure this,
install an additional heat generator in the heating circuit.
An elevating base and condensate tray heating are avail-
able as accessories.