Manual Pury 250e
Safety Instructions
Manual Pury 250e 2006-06-08
5
1. Safety
Instructions
Before start up and use of the Pury 250E, please take time to carefully review
this manual and its contents. Observe all warnings, cautions and notes.
Warning:
Disconnect the main power switch before any service work is carried out.
Before maintenance or repair work on the power or high voltage ignition
equipment, the following points need to be observed.
After switching off the main power wait at least 5 min. for any stored voltage
charge to dissipate to zero.
During start up, service or abnormal conditions there is a danger of a very
small release of unburned gas from the outlet of the system to the atmosphere.
If process gas has any toxic components please follow all personal safety
rules. Any small release of gas during start-up is highly diluted with cooling
air.
All electrical connections to line power must be carried out by a qualified electrician.
The analyzers internal electrical components are wired in accordance with NEC, VDE
and International standards. Check the power supply voltage, details can be found on
the technical data label inside the door.
Only qualified personnel should install the gas connections in accordance with all
local codes and ordinances.
The Pury 250E operates over a specified ambient temperature range. and installing
the unit directly outside is not recommended, since damage may occur from adverse
weather conditions if an outdoor shelter is not used.
Caution:
Caution is necessary during installation because pressurized flammable gases are
connected to the sample conditioner and any installation work performed by the
customer must conform to all applicable local and national codes. All internal sample
gas components have been leak tested at 1.5 times the normal operating pressure
during assembly at the factory. After installation, the entire sample gas system
should be pressurized and tested for leaks before use.
When planning the installation, local site conditions must be taken into account so
consult any hazardous area regulations for applicability.
Summary of Contents for Pury 250e
Page 1: ...Users Manual Pury 250e Gas Purification System ...
Page 6: ...Introduction Manual Pury 250e 6 Manual Pury 250e 2006 06 08 ...
Page 8: ...Installation Manual Pury 250e 8 Manual Pury 250e 2006 06 08 ...
Page 14: ...Commissioning Manual Pury 250e 14 Manual Pury 250e 2006 06 08 ...
Page 18: ...Maintenance Manual Pury 250e 18 Manual Pury 250e 2006 06 08 ...
Page 22: ...Circuit Diagrams Manual Pury 250e 22 Manual Pury 250e 2006 06 08 ...