PART II: INSTALLATION
21
Integrated proving system (burners equipped with LME7x, LMV, LDU)
This paragraph describes the integrated proving system operation sequence:
At the beginning both the valves (EV1 and EV2) must be closed.
Test space evacuating: EV2 valve (burner side) opens and keep this position for a preset
time (td4), in order the bring the test space to ambient pressure.Test atmospheric pressure:
EV2 closes and keep this position for a preset time (test time td1). The pressure switch
PGCP has not to detect a rise of pressure.
Test space filling: EV1 opens and keep this position for a preset time (td3), in order to fill the
test space.
Test gas pressure: EV1 closes and keep this position for a preset time (td2). The pressure
switch PGCP has not to detect a pressure drop down.
If all of the test phases are passed the proving system test is successful, if not a burner lockout
happens.
On LMV5x and LMV2x/3x and LME73 (except LME73.831BC), the valve proving can be
parameterized to take place on startup, shutdown, or both.
On LME73.831BC the valve proving is parameterized to take place on startup only.
PS
EV1
EV2
/
EV2
EV1
PGCP
Summary of Contents for E115X-FGR M Series
Page 42: ......
Page 43: ......
Page 45: ...Siemens LMV5x Service Manual M12920CC rev 2 1 08 2017...
Page 52: ...8...
Page 56: ...12 2 2 LMV5x program structure...
Page 83: ...39...
Page 90: ......
Page 91: ......
Page 92: ...Note Specifications and data subject to change Errors and omissions excepted...
Page 94: ...Annex1 Example for motor cable...
Page 95: ......
Page 96: ...Annex 2 Example for sensor cable...
Page 97: ......
Page 98: ......
Page 102: ......