Planning a OpenScape Cordless IP System
c03.fm
Determining the Installation Site
A31003-C1020-S100-03-7620, 12/2017
40
OpenScape Cordless IP V2, Service Documentation
3.4 Determining the Installation Site
3.4.1 Indoors
3.4.1.1 In Buildings of Brick or Light Construction Materials
•
Horizontal direction
A base station must be installed at least every 50 m.
•
Central installation in the building
The general rules must be observed.
•
Vertical coverage
Care must be taken to ensure that no more than two reinforced concrete
ceilings are in the direct propagation route between the base station and
the area of movement of the handsets.
Other base stations must then be set up in the radio cells if necessary,
based on the concentration of stations or the number of handsets.
Assuming that the distribution of handsets in buildings will be fairly uniform,
additional base stations should preferably be installed on the floors above or
below the minimum required base stations (see Figure 11).