27
Tec
hnical f
eatures and dimensions
3.16 - HYDRAULIC AND ELECTRICAL
SYSTEM CONNECTION
The following figures show the typical layout of the connection
of the boiler to the heating system with production of domestic
hot water.
Remember that TERNOX boilers operate with forced circulation.
Key:
Pr =
recirculation pump
VM = zone mixing valve
Pi =
heating system pump
VE = expansion vessel
IR =
heating system distribution
Ps = domestic water recirculation pump
Pc = domestic hot water production charge pump
TA = room thermostat
The standard panel board of the TERNOX boiler automatically
switches the burner off when the temperature in the boiler reach-
es the value set on the control thermostat.
It also manages the C.H. pump, which will only be activated
when the minimum boiler temperature of 50°C has been reached
(anti-condensation protection temperature).
The pump will switch off when the lower threshold of 50°C (de-
creasing) is reached.
The panel is set up to manage dual-stage or modulating burners.
With this layout configuration, the DHW storage tank loading
pump will have the priority over the heating C.H. pump.
TERNOx BOILER
DOMESTIC HOT WATER
PRODUCER