Figure 8: Baffle Orientation in Flueways
Step a.
Install stainless steel baffles provided in
miscellaneous parts carton as follows, refer to Table
3 and Figure 8:
•
Model MPO-IQ84 - To install flueway baffle in 3
rd
pass on left side of boiler, hold baffle with word
"Left" readable at the top. Slide baffle in flueway
until position tab touches fins on left side of 3
rd
pass flueway. To install flueway baffle in 3
rd
pass
flueway on right side of boiler, hold baffle with
word "Right" readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 3
rd
pass flueway.
•
Model MPO-IQ115 - To install flueway baffle in
3
rd
pass on left side of boiler, hold baffle with word
“Left” readable at the top. Slide baffle in flueway
until position tab touches fins on left side of 3
rd
pass flueway. To install flueway baffle in 3
rd
pass
flueway on right side of boiler, hold baffle with
word “Right” readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 3
rd
pass flueway. To install flueway baffle
in 2
nd
pass on left side of boiler, hold baffle with
word “Left” readable at the top. Slide baffle in
flueway until position tab touches fins on left side
of 3
rd
pass flueway. To install flueway baffle in 2
nd
pass flueway on right side of boiler, hold baffle
with word “Right” readable at the top. Slide
baffle in flueway until position tab touches fins
on right side of 3
rd
pass flueway.
•
Models MPO-IQ147, MPO-IQ189 and MPO-
IQ231 - To install flueway baffle in 2
nd
pass
flueway on left side of boiler, hold baffle with
word "Left" readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 2
nd
pass flueway. To install flueway baffle
in 2
nd
pass flueway on right side of boiler, hold
baffle with word "Right" readable at the top. Slide
baffle in flueway until position tab touches fins
on left side of 2
nd
pass flueway.
NOTE:
2
nd
and 3
rd
pass flueway baffle are not
interchangeable.
6.
Close the burner swing door
and securely seal the door
to the boiler front section by reinstalling the hardware and
securing the door using procedure previously outlined in
Paragraph D of this section.
NOTICE
When securing burner swing door make sure door
is drawn-in equally on both sides.
II. PACKAGED BOILER ASSEMBLY - TRIM & CONTROLS (cont'd)
Summary of Contents for MPO - IQ
Page 6: ...6 Figure 1 MPO IQ84 Thru MPO IQ231 Water Boiler ...
Page 22: ...22 Figure 11 Boiler Removal from Skid III UNIT PAK BOILER ASSEMBLY TRIM CONTROLS continued ...
Page 42: ...42 Figure 28A Schematic Wiring Diagram VII ELECTRICAL continued ...
Page 43: ...43 Figure 28B Schematic Wiring Diagram Burner Options VII ELECTRICAL continued ...
Page 44: ...44 Figure 28C Ladder Diagram VII ELECTRICAL continued ...
Page 70: ...70 Bare Boiler Assembly XIV Repair Parts continued ...
Page 72: ...72 Jacket Assembly XIV Repair Parts continued ...
Page 74: ...74 MPO IQ84 Thru MPO IQ231 Water Boilers Trim and Controls XIV Repair Parts continued ...
Page 78: ...78 Beckett AFG Burner XIV Repair Parts continued ...
Page 80: ...80 Beckett NX Burner XIV Repair Parts continued ...
Page 92: ...92 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...