4.3
Commissioning
When the hydraulic system is filled and ready for operation, connect the power
unit to the mains.
The controller has to be connected to the power unit (already connected) and to
the measuring unit by means of the VBus
®
.
The controller runs an initialisation phase in which the Lightwheel
®
glows red.
When the controller is commissioned or when it is reset, it will run a commis-
sioning menu after the initialisation phase. The commissioning menu leads the user
through the most important adjustment channels needed for operating the system.
Commissioning menu
The commissioning menu consists of the channels described in the following. In
order to make an adjustment, adjust the desired value with the Lightwheel
®
and
confirm with the right button (
✓
). The next channel will appear in the display.
Adjustment mode
Operation
Changing a value
Confirming a value
Next parameter
1. Language:
Î
Adjust the desired menu language.
2. Daylight savings time adjustment:
Î
Activate or deactivate the automatic daylight sav-
ings time adjustment.
3. Date:
Î
Adjust the date. First of all adjust the year, then the
month and then the day.
4. Time:
Î
Adjust the clock time. First of all adjust the hours,
then the minutes.
5. Target temperature:
Î
Adjust the desired target temperature.
6. Maximum return temperature (maximum
store temperature):
Î
Adjust the desired maximum return temperature.