21. Mount Power Unit (Item # 62) to the Mainside Column with the attached mounting bracket
using the hardware provided, shown in Figure # 10. Once mounted, fill the Power Unit
reservoir tank with hydraulic fluid.
22. Install the 90 degree Hydraulic Fitting, Nuts & Washer (# 90, 91, 92 & 93) to the high pressure
port on the Power Unit, shown in Figure 10. Connect the 115VAC electrical power to the Power
Unit.
23. Install the
“wire braided” Hydraulic Hose (#89) to the Fitting on the side of the Main side
Runway and attach the other end to the 90 degree Fitting on the Power Unit, as shown in
Fig.10.
Fig. 10
24. Now raise the complete unit (Lift) and set at one of the bottom lock positions. Place level on
crossbeam.
25. Tighten Lock Ladder Rod Nut located on the top of each Column. This will raise the corner of
the lift to adjust for leveling. Each Column has this adjustment. Adjust the proper columns to
level the lift. Place a level on each runway and crossbeam and check for proper levelness.
Note: You may have to loosen the Jam Nut under the Top Cap to make adjustments.
(Also see Exploded View
Details on Page 25)
Summary of Contents for FP8K-B
Page 23: ...23 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 1...
Page 24: ...24 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 2...
Page 25: ...25 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 3...
Page 26: ...26 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 4 41...
Page 27: ...27 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 5...