16. Begin cable routing installation to Column Top Caps by first ensuring the pre-installed steel
Cables are properly routed around each Cable Sheave and are not in a bind.
17. Pull the slack for each Cable from the corner ends of the Mainside Runway and route the
appropriate Cable(s) to each Column Top Caps, while ensuring that the Crossbeam
’s Cable
Pulley is between the Cable and the Lock Ladder as shown in Fig.6. This will allow the
secondary Slack Cable Lock to function properly. See Fig.6 below for Cable routing
installation.
Fig. 6
18. Install Cable Guide Bolts & Nuts (#21B) to the underside of the Mainside Runway at each end,
as illustrated in Fig. 7. Four Guide Bolts will be installed at one end and two at the other end.
Note: Cable Guide Bolts assists in keeping the Cables properly engaged to the Pulleys.
Fig. 7
Nylon Lock Nut
& Washer
Cable Pulley
Cable Guide Bolts
Summary of Contents for FP8K-B
Page 23: ...23 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 1...
Page 24: ...24 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 2...
Page 25: ...25 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 3...
Page 26: ...26 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 4 41...
Page 27: ...27 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 5...