27
BESS installation
– BESS connections
Connecting the AC cables
Step 1
: Connect to the
grid
:
Actives:
A) Wire the
Grid AC breaker
B) Wire to the
Energy Meter
Neutrals
:
A) Wire to the
Neutral busbar
Earth
:
A) Wire to
busbar
B) Busbar to the
mains earth
L
N
E
L
N
Critical Load
Energy Meter
To Energy Meter
Step 2:
Connect to the
critical load
Actives:
A) Wire the
Critical load AC breaker
B) Wire to the
critical load
Neutrals:
A) Wire straight to
critical load
Earth:
A) Wire to
busbar
Summary of Contents for PowerCube 2.0 DC
Page 1: ...PowerCube 2 0 DC Installation Guide Australia New Zealand Feb 2018 V1 5...
Page 3: ...System Introduction 01 System Topology Power Box DC PowerCube 2 0...
Page 5: ...5 Power Box DC Bess Hybrid Inverter Length 610mm Width 515mm Height 192mm Weight 30kg...
Page 7: ...Upacking the products 02 Battery Packs PowerCube 2 0 Casing Power Box...
Page 8: ...8 Battery Packs...
Page 12: ...12 Installation Tools Hammer Drill Recommend drill dia 8 10mm...
Page 14: ...14 System Connection Single Line Diagram TB5200SH internal wiring diagram...
Page 22: ...22 System connection Battery Modules 4 Packs Connection Wire Master Energy Meter...
Page 29: ...29 BESS installation Complete Note Sample Installation for reference...
Page 45: ......