Trinabess PowerCube 2.0 DC Installation Manual Download Page 27

27

BESS installation 

– BESS connections

Connecting the AC cables

Step 1

: Connect to the 

grid

Actives:

A) Wire the 

Grid AC breaker

B) Wire to the 

Energy Meter

Neutrals

:

A) Wire to the 

Neutral busbar

Earth

:

A) Wire to 

busbar

B) Busbar to the 

mains earth

L

N

E

L

N

Critical Load

Energy Meter

To Energy Meter

Step 2: 

Connect to the 

critical load

Actives:

A) Wire the 

Critical load AC breaker

B) Wire to the 

critical load

Neutrals:

A) Wire straight to 

critical load

Earth:

A) Wire to 

busbar

Summary of Contents for PowerCube 2.0 DC

Page 1: ...PowerCube 2 0 DC Installation Guide Australia New Zealand Feb 2018 V1 5...

Page 2: ...2 Contents 1 System Introduction 2 Unpacking the products 3 System Installation Steps 4 WIFI Monitoring Setup Guide...

Page 3: ...System Introduction 01 System Topology Power Box DC PowerCube 2 0...

Page 4: ...inly applied and developed for the renewable energy generation system The interface between the grid solar PV and the battery storage Designed for lithium ion batteries PowerCube Battery Energy Storag...

Page 5: ...5 Power Box DC Bess Hybrid Inverter Length 610mm Width 515mm Height 192mm Weight 30kg...

Page 6: ...city and convenience Can be completed by one person Integrated Isolator design to reduce the cost and time required for installation Outdoor rating IP54 Length 1000mm Width 600mm Height 210mm Weight a...

Page 7: ...Upacking the products 02 Battery Packs PowerCube 2 0 Casing Power Box...

Page 8: ...8 Battery Packs...

Page 9: ...Casing 1 B Battery Pack Power Cable with connectors connecting between battery packs 6 C RJ45 communication line with connectors 3 D Connectors without Power Cable 2 E RJ45 communication connectors 2...

Page 10: ...10 Power Box DC Communication Cable Adapter Anderson plug connector Batt Aviation Plug Female Aviation Plug Male Plug Screw Fixings Solar PV connect 2 pairs...

Page 11: ...System Installation Steps 03 Installation tools and accessories Single Line Diagram Powerbox installation Powercube installation BESS installation System Initialization System Setting...

Page 12: ...12 Installation Tools Hammer Drill Recommend drill dia 8 10mm...

Page 13: ...ext to the BESS system and inside the main switchboard Additional ones for extended distance away from switchboard distribution board AC cables 4mm2 From powerbox to Switchboard Distribution board cri...

Page 14: ...14 System Connection Single Line Diagram TB5200SH internal wiring diagram...

Page 15: ...rough bracket to expansion tube adjust the bracket position and screw in 6 Align with wall bracket move Powerbox DC in horizontal direction to proper position 7 Make the hook on wall bracket insert in...

Page 16: ...Step 3 Use the cardboard template provided to do wall mount hole marking and drill holes accordingly Step 4 Insert wall plug and drive the M8 bolts Note Place two anti theft bolts in the middle hole...

Page 17: ...17 Powercube installation Battery packs Once the Powercube enclosure have been secured with bolts Step 1 Insert the packs into the mounted casing Step 2 Turn the baffle to secure the battery packs...

Page 18: ...Step 3 Connect the positive cables Note for better performance connect the breaker positive cable to the last battery pack Step 4 Connect the inverter comms cable to Master only Step 5 Connect the co...

Page 19: ...tem connection Powercube Battery pack overview CP 1 Cathode CP 6 Link Port 1 CP 2 Cathode CP 7 CAN CP 3 Anode CP 8 RS485 CP 4 Anode CP 9 POWER ON OFF CP 5 Link Port 0 CP 10 Soft Starter Connection Poi...

Page 20: ...em connection Battery Modules 2 Packs Connection Wire Powerbox DC DC isolator supplied Powercube battery packs Master Link 1 Link 0 Comms Relay Plate supplied DC Positive cable Energy Meter DC Negativ...

Page 21: ...21 System connection Battery Modules 3 Packs Connection Wire DC isolator supplied Powercube battery packs Master Powerbox DC Energy Meter Comms Relay Plate supplied Link 0 Link 1 Link 0 Link 1...

Page 22: ...22 System connection Battery Modules 4 Packs Connection Wire Master Energy Meter...

Page 23: ...23 BESS installation BESS connections Position the BESS distribution box recommend 4 pole Breaker Negative cable Inverter comms cable Breaker Positive cable 200mm 100mm...

Page 24: ...o Inverter comms cable Inverter to Battery comms cable Position the BESS distribution box recommend 4 pole 1 Prepare and run the comms cables AC cables and conduit if applicable to the DB 2 Prepare an...

Page 25: ...repare the AC Grid and Critical load connectors 2 Connect the AC connectors to the inverter 3 Connect the Anderson plug to the DC cables 4 Connect the comms cable to RS485 port 5 Run the battery comms...

Page 26: ...led Step 1 Insert the relay board on to the DIN rail Step 2 Connect inverter comms cable to relay board Step 3 Insert the powercube comms cable positive to 3 negative to 6 Step 4 Run the energy meter...

Page 27: ...o the Energy Meter Neutrals A Wire to the Neutral busbar Earth A Wire to busbar B Busbar to the mains earth L N E L N Critical Load Energy Meter To Energy Meter Step 2 Connect to the critical load Act...

Page 28: ...Breaker may be needed for local wiring requirements Step 3 Connect energy meter to main circuit breaker Step 4 Connect Normal loads to energy meter circuits Step 5 Connect Earth circuit E L N Critica...

Page 29: ...29 BESS installation Complete Note Sample Installation for reference...

Page 30: ...BESS system per the following steps 1 Turn ON PV array isolators circuit breakers if applicable 2 Turn ON AC circuit breaker between Power Box Grid port Grid The Power Box should start to operate now...

Page 31: ...d to next item or next page OK Enter Escape Enter into or exit from the current page Item Definition Description System operation light Light on when hybrid inverter system is running smoothly Battery...

Page 32: ...04 PV parallel MDE Operation mode 00 PV self of use default 01 Forced Time of Use TOU 00charging time 01discharging time 02 Back up reserved 04 Slave mode ADR Meter address 001 255 CT Current transfor...

Page 33: ...to be changed 1 At the standard interface long press the OK button for 3 seconds to enter the setting menu 2 Input the password 1111 3 Choose parameters by pressing buttons Go into TIM which refers to...

Page 34: ...rd interface long press the OK button for 3 seconds to enter the setting menu 2 Input the password 1111 3 Choose parameters by pressing buttons Go into ADR which refers to smart meter address 4 Check...

Page 35: ...ged 1 At the standard interface long press the OK button for 3 seconds to enter the setting menu 2 Input the password 1111 3 Choose parameters by pressing buttons Go into CT which refers to CT address...

Page 36: ...face long press the OK button for 3 seconds to enter the setting menu 2 Input the password 1111 3 Choose parameters by pressing buttons Go into FED which refers to Grid feed in power 4 Grid feed in po...

Page 37: ...plicable 3 Turn ON AC circuit breaker between Power Box Grid port Grid The Power Box should start to operate now 4 Turn ON all the battery packs by pressing any one of the red softstart button on the...

Page 38: ...ge on grid EMERGENCY LOAD voltage off grid EMERGENCY LOAD current off grid TEM Inverter Temperature FRE Grid frequency ET1 Daily PV production SOC Battery capacity SWC software version No of SolDate52...

Page 39: ...WIFI Monitoring Setup Guide 04 Establish WLAN Wi Fi Connection APP Setup BESS System Monitoring...

Page 40: ...the Inverter Wi Fi SSID which is same as inverter serial number Open up an internet browser using a computer PC or from any smart device Enter the inverter IP address in the address bar URL to open u...

Page 41: ...al WiFi network SSID and password OR go to Find AP to choose one of the SSID from the list Enter the password into the Key table Click Save Reboot and restart wait at least 2 minutes If the device IP...

Page 42: ...n when Username is created it cannot be changed Email Address fill in a frequently used email address in case of forgetting the actual password Hybrid the type of your device it can be selected Hybrid...

Page 43: ...43 APP setup Downloading the APP Search Trinabess in app store IOS For android download via this link or QR code http cloud trinabess com TrinabestAgent resources app trinabess apk...

Page 44: ...44 BESS System monitoring Demo account Webpage http cloud trinabess com Username pan1 Password 123456 2 1 2 2 2 3 2 5 2 4 2 4 1 2 4 3 2 4 2 2 4 5 2 4 4 2 6...

Page 45: ......

Reviews: