Powercube installation
– BESS connections
Connecting the packs together
Step 1
: Connect a
master
pack. The master should have the
breaker Negative cable
connected to it. It should also have the
label
“Master Mode”
Step 2:
Connect rest of the
negative
cables
Step 3
: Connect the
positive cables
.
Note: for better performance, connect the breaker positive cable to
the last battery pack.
Step 4
: Connect the
inverter comms cable
(to Master only)
Step 5:
Connect the
comms cable
between the battery packs
Step 6
: Measure the
required distance from powercube to
Powerbox
& prepare a positive and negative DC cable and
connect to battery breaker
Slave
Master
Breaker Negative cable
Inverter comms cable
Breaker Positive cable
Summary of Contents for PowerCube 2.0 DC
Page 1: ...PowerCube 2 0 DC Installation Guide Australia New Zealand Feb 2018 V1 5...
Page 3: ...System Introduction 01 System Topology Power Box DC PowerCube 2 0...
Page 5: ...5 Power Box DC Bess Hybrid Inverter Length 610mm Width 515mm Height 192mm Weight 30kg...
Page 7: ...Upacking the products 02 Battery Packs PowerCube 2 0 Casing Power Box...
Page 8: ...8 Battery Packs...
Page 12: ...12 Installation Tools Hammer Drill Recommend drill dia 8 10mm...
Page 14: ...14 System Connection Single Line Diagram TB5200SH internal wiring diagram...
Page 22: ...22 System connection Battery Modules 4 Packs Connection Wire Master Energy Meter...
Page 29: ...29 BESS installation Complete Note Sample Installation for reference...
Page 45: ......