BESS installation
– BESS connections
Connecting the comms cables
(cables already labelled)
Step 1
: Insert the
relay board
on to the
DIN rail.
Step 2
: Connect
inverter comms cable
to
relay board
Step 3
: Insert the
powercube comms
cable
positive
to
3
,
negative
to
6
Step 4:
Run the
energy meter comms
cable
to the energy meter (to be located
on the main switchboard)
To Energy Meter
Summary of Contents for PowerCube 2.0 DC
Page 1: ...PowerCube 2 0 DC Installation Guide Australia New Zealand Feb 2018 V1 5...
Page 3: ...System Introduction 01 System Topology Power Box DC PowerCube 2 0...
Page 5: ...5 Power Box DC Bess Hybrid Inverter Length 610mm Width 515mm Height 192mm Weight 30kg...
Page 7: ...Upacking the products 02 Battery Packs PowerCube 2 0 Casing Power Box...
Page 8: ...8 Battery Packs...
Page 12: ...12 Installation Tools Hammer Drill Recommend drill dia 8 10mm...
Page 14: ...14 System Connection Single Line Diagram TB5200SH internal wiring diagram...
Page 22: ...22 System connection Battery Modules 4 Packs Connection Wire Master Energy Meter...
Page 29: ...29 BESS installation Complete Note Sample Installation for reference...
Page 45: ......