1
SPARE PARTS
INSTRUCTIONS # 51
Date Created:
31/05/2017
Product:
Warlord S3
Title:
Rotor Removal and Replacement
SAFETY!
Before attempting to make any adjustments or carry out maintenance on the mower, review
the hazard identification table (section 3a of your Operator Manual) and take all necessary precautions.
Due to the specialized nature of Rotor removal and replacement, it is recommended that this procedure is
only attempted at a fully equipped General Engineering Workshop.
Read through this entire process prior to starting. Take note of where parts are removed from!
Ensure all appropriate protective equipment is used.
Heavy Lifting Equipment is required for this process, ensure all Lifting Equipment is suitably rated!
REQURIED SHIM THICKNESS
Warlord Series 3 Mowers:
0.45 – 0.5mm (0.018 – 0.020”) thick.
IMPORTANT:
Two strips of shim material are required for this
operation.
These should be a little longer than one side of the
square rotor bearing housing and about
10-15mm
(3/8 - 5/8”)
wide.
Use the Tractor hydraulics to position the
Headstock
CENTRALLY
in relation to the
Mower.
Disconnect the Warlord S3 and P.T.O Shaft from
the Tractor.
Remove the P.T.O Shaft from the Warlord S3.
This is detailed in the Operators Manual for the
Mower.
IMPORTANT:
A Warlord S3 175 Right-Hand Offset is shown
opposite, however this process applies for
ALL
models and sizes.
The end with the Pulleys is
ALWAYS
referred to
as the
DRIVE END
. If your Warlord S3 is a
Left-Hand offset, the drive end will be
OPPOSITE
to what is shown. However, the
process is
IDENTICAL
!
DRIVE END