TRANE AHU Pre-start up Checklist
General Information
Date
Project Name:
Trane Sales Order #
Trane AHU Model
Unit Serial No.:
Unit TAG #
Design Capacity (CFM) @ Design ESP
AHU Location
Area Served
Start-Up Contractor
T & C Technician / Engineer
Casing Installation Check
Exterior casing in good condition
Interior casing in good condition
Is the unit installation level?
Are the unit clearances adequate for service and operation?
Do all access doors open freely and are the handles operational?
Fan-Motor Installation Checks
Have all shipping braces / brackets been removed?
Fan and Motor Alignment correct
Belt tension & condition good
Belt guard in place and secure.
Do the fan rotates freely?
Electrical Installation Checks
Electrical Cable entry at unit wall & motor terminal box is sealed.
Have all electrical connections been tested for tightness?
Insulation test done on motor winding.
Has overcurrent protection been installed to match unit nameplate
requirement?
Does the electical supply correspond to the unit nameplate?
External Power Disconnects in place and labeled.
Proper grounding Installed for motor and unit.
Motor Nameplate FLA
Installed Motor kW
Electrical Power Supply
Voltage Imbalance
Supply Fan
Amp
kW
Vac/Ph/Hz
%
Return / Exhaust Fan
Amp
kW
Vac/Ph/Hz
%
63
Pre-Start Up Checklist
ohm
ohm
Summary of Contents for TRANE Quantum CLCPEuro
Page 2: ...TRANE R...
Page 6: ...TRANE R 2 CLCPXP Model Nomenclature...
Page 7: ...TRANE R CLCPEURO Model Nomenclature 3...
Page 13: ...TRANE R Assembly Installation CLCPEuro CLCPXP External connection 9...
Page 14: ...TRANE R Assembly Installation CLCPEuro Break Point 25mm Frame to Frame 10...
Page 15: ...TRANE R 11 Assembly Installation CLCPEuro Break Point 25mm Panel to Frame...
Page 16: ...TRANE R 12 Assembly Installation CLCPEuro Break Point 2 50mm Frame to Frame...
Page 17: ...TRANE R Assembly Installation CLCPEuro Break Point 2 50mm Panel to Frame 13...
Page 18: ...TRANE R Assembly Installation CLCPEuro Paneling 14...
Page 19: ...TRANE R Assembly Installation CLCP XP Break Point 15...
Page 20: ...TRANE R Assembly Installation CLCP XP Break Point 16...
Page 21: ...TRANE R 17 Assembly Installation CLCP...
Page 22: ...TRANE R Assembly Installation CLCP 18...
Page 36: ...TRANE R Maintenance 32 Figure 18 Belt Tension Measurement...
Page 39: ...TRANE R 35 Trouble Analysis Pulley and Belt...
Page 45: ...TRANE R Appendix B HDT Unit Weight CLCPXP 41...
Page 46: ...TRANE R Appendix B HDT Unit Weight CLCPXP 42...
Page 47: ...TRANE R Appendix B HDT Unit Weight CLCPXP 43...
Page 48: ...TRANE R Appendix B VDT Unit Weight CLCPXP 44...
Page 53: ...TRANE R Appendix D Filter and Quantity 49 Filter Dimension and Arrangement Final Filter HEPA...
Page 57: ...TRANE R Typical Wiring Diagram Starter Star Delta 380 420V 3Phase 4Wires ELCB Standard 53...
Page 58: ...TRANE R 54 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires ELCB Standard...
Page 59: ...TRANE R 55 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires Standard...
Page 62: ...TRANE R 58 Typical Wiring Diagram Starter Dol 380 420V 3Phase 4Wires Standard...
Page 65: ...TRANE R 61 Typical Wiring Diagram Starter Star Delta 380 420V 3Phase 4Wires Standard...
Page 68: ...TRANE R 64...
Page 70: ...TRANE R 66...
Page 71: ...TRANE R...