RT-SVX25C-EN
33
Installation
Use the checklist provided below in conjunction with the “General Unit Requirements” checklist to
ensure that the unit is properly installed and ready for operation.
WARNING
Hazardous Voltage!
Disconnect all electric power, including remote disconnects before servicing. Follow proper
lockout/tagout procedures to ensure the power can not be inadvertently energized. Failure to
disconnect power before servicing could result in death or serious injury.
•
Check all electrical connections for tightness and “point of termination” accuracy.
•
Verify that the condenser airflow will be unobstructed.
•
Verify that the condenser fan and indoor blower turn freely without rubbing and are properly
tightened on the shafts.
•
Check the supply fan belts for proper tension and the fan bearings for sufficient lubrication. If
the belts require adjustment, or if the bearings need lubricating, refer to the maintenance
section of this manual for instructions.
•
Verify that a condensate trap is installed and the piping is properly sized and pitched.
•
Verify that the correct size and number of filters are in place.
•
Inspect the interior of the unit for tools and debris and install all panels in preparation for
starting the unit.
Figure 19. Space temperature averaging examples