47
TRIAD Boiler Systems, Inc.
West Chicago, IL
www.triadboiler.com
18.
Immediately after burner shuts off, inspect water pressure and open the highest vent to
determine that system is completely full of water.
19.
Enter into log book: Time and date of startup, any irregularities observed and corrective action
taken. Time when control shut off burner at established pressure/temperature, tests performed,
etc.
20.
Check safety relief valve(s) for evidence of leaking. Perform try lever test.
See safety relief valve
operating information.
6.9 Good Practice recommendations for hot water boilers
NOTE: Use of this hot water boiler for temporary heating of an unfinished building is not recommended
by TRIAD. Use of the boiler prior to closing the building and balancing of the heating system may lead to
thermal shock and leakage. Use of the boiler for temporary heat will render the warranty void against
leakage.
1.
Do not put into service for any purpose without properly balancing the heating system and properly
adjusting the burner.
2.
The burner must be adjusted to avoid short term cycling. This will help eliminate the problems
connected with rapid expansion and contraction associated with short cycling when the burner is not
modulating continuously.
3.
The firing rate of the unit must not be exceeded.
4.
A circulation flow switch (when a circulation pump is provided) must not permit the burner to fire
unless water from the heating system is circulating through the boiler.
5.
Prior to initial start-up, the entire heating system must be cleaned of all foreign matter such as rust,
oil, etc.
6.
Proper water treatment must be used.
7.
Boiler operating personnel should be properly trained in maintenance and operating procedures.
6.10 Guide lines for hot water boiler heating system.
Condition: Boiler Warm – System Warm
Start burner on low fire only.
Open supply and return headers and start system pump.
After boiler and system temperature are equal, release burner to automatic.
Shut down of hot water boiler heating system
Put manual low fire hold switch in low fire hold position.
Summary of Contents for Triumph 1000
Page 14: ...14 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Handling Options ...
Page 20: ...20 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Model 300 500 Model 750 1000 ...
Page 27: ...27 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com 2 6 Example wiring diagrams ...