4.
Disconnect all the port connections:
•
Power AC mains in: unscrew the two connector flange screws using a slotted SL3 screwdriver
•
Logic AC mains in: unscrew the two connector flange screws using a slotted SL3 screwdriver
•
LAN1 and LAN2: disconnect STP cable (if applicable)
•
CEDD
®
Power out: press down firmly on the red clips, pull back the clips, then remove the
connector from the CEDD
®
HPS Basestation
Power AC Mains In
Logic AC Mains In LAN1
LAN2
CEDD
®
Power out
5.
Disconnect the protective earth of the cabinet using an M4 (7 mm) hex socket with a ratcheting
socket wrench (or equivalent).
6.
Loosen the four supporting bolts of the CEDD
®
HPS Basestation using an open-ended wrench
(10 mm), making sure there is space of 4 to 8 mm (A) to allow the cabinet to be lifted.
Installation and Maintenance Manual - CEDD
®
HPS Basestation
©
TKH Airport Solutions 2022. All rights reserved. All specifications subject to change without notice.