![The Fire Dept GD3 Installation Manual Download Page 10](http://html1.mh-extra.com/html/the-fire-dept/gd3/gd3_installation-manual_1099697010.webp)
21-3-2017 VERSION 4 Page
of
10
20
•
Following these connection details, using the 4 core cable that has been run at site, connect the switch to the fire.
•
IMPORTANT: Before testing, ensure the gas valve is turned off.
•
Test electrical functions by switching the bottom High/Low switch to LOW, then switch the fire ON using the top On/Off switch.
•
The fan will start and after approximately five seconds, the pilot will spark. Because the gas supply is turned off, the pilot will spark
for approximately five seconds then automatically switch off. The fan will continue running.
•
NOTE:
GD3 models have a fan which runs in both LOW and HIGH settings.
•
Switch to HIGH setting. Ensure that a red light appears on electrical connections block and the fan is running.
•
Switch fire off. Electrical testing is complete.
•
Replace the burner tray by following the
‘Burner Tray Installation Process’
in Step 3 of this guide.
•
Carefully replace glass by simply reversing the glass removal process.
Summary of Contents for GD3