1.2
Installation Prerequisites
For the installation to proceed without interruption, it is important that you have all necessary materials
on hand.
800 Series Standalone
800 Series 1+1 System
Adequate space for the installation of the 800
series standalone.
You will need to mount the 800 series unit on a
19" equipment rack (customer provided). Your
800 series unit is a 1U unit.
Adequate space for the installation of the 800
series 1+1 system.
You will need to mount the 800 series 1+1
system on a 19" equipment rack (customer
provided).
The 1+1 System requires space for the following
number of units:
Adequate power supply and power
connections.
The 800 series unit requires two power
connections. To guarantee an uninterrupted
supply of electricity, each power connection must
be fed by a dedicated power source.
IP addresses for the management ports.
To avoid delays, you should have the IP address,
netmask and gateway addresses on hand. Take
note that the management port supports DHCP,
see
2.4.1 “Connecting to the 800 Series
Gateway Management Interface” on page
14 for
further information.
800 Series Unit:
800 1 Unit:
1+1 Patch Panel(s):
Total:
1U
1U
1U/2U
3U/4U
Adequate power supply and power
connections.
The 800 series and 800 1 units require
two power connections each. To guarantee an
uninterrupted supply of electricity, each power
connection must be fed by a dedicated power
source.
IP addresses for the management ports.
To avoid delays, you should have the IP
address, netmask and gateway addresses on
hand. Take note that the management port
supports DHCP, see Section
Summary of Contents for 800 1+1 series
Page 1: ...Installation Guide 800 Series Gateway Standalone 800 Series Gateway 1 1 October 26 2015...
Page 37: ...31 Installing the Equipment 3 Once you confirm the changes a progress page is displayed...
Page 46: ...800 Series Standalone and 800 Series 1 1 System Installation Guide 40...
Page 54: ...800 Series Standalone and 800 Series 1 1 System Installation Guide 48...