For cabs equipped with air conditioning option, proceed with the following steps.
NOTE: With the compressor orientated the way it must be in this design, ALL of the pre-filled
oil in the compressor WILL pour out.
22. Take the hoses from the right C-post baffle, and route underneath the hood towards the
compressor.
23. Connect the # 10 hose to the #10 fitting on the compressor. Ensure O-ring is properly
seated!
24. Connect the # 8 hose to the # 8 fitting on the compressor. Ensure O-ring is properly seated!
25. Use the provided zip ties to tie the hoses into place and prevent them from contacting any
moving parts or hot surfaces.
26. Take the white wire that was with the air-conditioner hoses, along with the provided bullet
connector and connect the wire to the compressor clutch wire on the compressor. Shorten
wire as necessary.
27. Air conditioning system is now ready to be charged by a licensed air conditioning install
technician. The compressor is normally pre-filled with oil and should have 3.5 fluid oz of SP15.
The system requires 2 lbs of R-134a refrigerant.
NOTE: With the compressor orientated the
way it must be in this design, ALL of the pre-filled oil in the compressor WILL pour out.
June 2021© New Holland G6030/6035 ROPS Cab Installation Manual