5. System planning and installation
5.1 System planning
Tapsa Control central battery unit uses the circuit cabling to transfer data between the central battery
unit and the luminaires. This way there is no need for separate data cabling, and the circuit cabling can
be done in the same way as the regular cabling for emergency lighting system.
5.1.1 Luminaire-specific addressable monitoring
The following points should be taken into consideration when planning addressable monitoring:
The luminaires used in the system must be manufactured by Teknoware, and their type code
must end with a 'K' (For example TWT6081K) or external luminaires fitted with Teknoware
address module. These types of luminaires include the technology that allows communication
between the luminaire and the central battery unit.
The luminaires must be coded with addresses from 1 to 32. The addresses can be selected
freely as long as two or more luminaires in the same circuit do not have the same address. The
coding (circuit no. / luminaire no.) can be marked in accordance with the electrical plan to the
address label delivered with the luminaire.
5.1.2 Circuit monitoring
Circuit-specific condition monitoring allows the usage of any emergency luminaires operating on AC/DC
voltage. However, in case of the fluorescent lamp luminaires, they shall be designed so that they switch
off when the lamp fails. This is because the system measures only the current of the circuit and detects
the failures from the changes in it.
5.2 System installation
The system must be installed according to the electrical plan or work description.
If you use addressable monitoring, make sure that all luminaires belonging to the same circuit have a
different address number (between 1 and 32). Set the address by changing the DIP switch settings.
The DIP switch is located in the data transfer unit or electronic ballast inside the luminaire. The
instructions for setting the addresses are included in the luminaires' installation instructions.
To install the system,
1. Make sure that the main switch is in the '0' position and the battery fuses are removed.
The batteries are always placed in a separate battery case, and connected in series (18 x 12 V) to
the + (red) and - (black) cables reserved for them. The batteries' temperature sensor is placed
between the batteries.
2. Check the polarity of the batteries.
3. Connect the supply cable to connectors 1~ L, PE and N or 3~ L1, L2, L3, PE and N (F-models)
4. The output circuits are connected to connectors X1-X3.
The circuit fuses F1-F24 are located at connectors X1-X3. The central battery unit outputs can be
connected as maintained or non-maintained, using the "Mode" wire links in the following way:
Summary of Contents for TKT66
Page 40: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 40 TKT66 P...
Page 43: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 43...
Page 44: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 44...
Page 45: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 45...
Page 46: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 46...
Page 47: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 47...
Page 48: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 48...
Page 49: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 49...
Page 50: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 50...
Page 51: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 51...
Page 53: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 53...
Page 54: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 54...
Page 55: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 55...
Page 56: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 56...
Page 57: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 57...
Page 58: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 58...
Page 59: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 59...
Page 60: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 60...
Page 61: ...VOT1 Rev 1 5 EN 5 11 2015 TKT66 Installation and maintenance 61...